City of Cuthbert FY15 CDBG Sewer System Improvements Lance Renfrow River Valley Regional Commission
2
Project Location City of Cuthbert Randolph County
4
Project Selection Public Works knew of faulty sewer lines and overflows Site visits to see the problems Engineer and Public Works examined old sewer plans to determine target area Multi-phase project most feasible to adequately address the problem
5
Project Background Existing sewer lines built in 1950s Significant groundwater inflow and infiltration Project Specifications – Install 2,300 L.F. of 15” new sewer main – Install 4,550 L.F. of 8” new sewer main – 3 manholes replaced – 18 manholes rehabilitated – $419,258
7
Gathering Information Investigation – City Council, City Clerk, and Public Works are key players Photos EPD letter of noncompliance with high levels of Ammonia – Evidence of inflow and infiltration – Surveys Door to door, water bill payments – Letters of Support Obtained at time of survey – Engineer Engineering report helps with DCA 4 and 5
8
Paint a Picture DCA 4 – Demographics Costs to repair sewage backups furthers financial burden – Health Hazards Sewage flows into adjacent stream (photo documentation) Sewage backs up into homes (letters of support) Sewage near school playground
9
Take Pictures
13
Bonus Points Revitalization Area Strategy Environmental Assessment No acquisition needed Engineer/Administration procurement
14
City of Cuthbert FY15 CDBG Sewer System Improvements Lance Renfrow LRenfrow@rivervalleyrc.org River Valley Regional Commission