Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning
3
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning
4
Q806 arrives
6
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning
8
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning
9
Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!
12
Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!
14
Bias Supplies
15
Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!
16
MI8 Excavation
17
Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!
18
Reminder 13.8KV Transformer/Switchgear Replacement - Prepare for next week's transformer/switchgear work - 208V work - Schedule for power outage and switch to generator -0700 to 12:00 for electrical work and switch over to generator Monday March 27 -This will effect BET, BEG and Booster Tunnel