Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.

Similar presentations


Presentation on theme: "Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before."— Presentation transcript:

1 Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning

2

3 Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning

4 Q806 arrives

5

6 Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning

7

8 Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning

9 Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!

10

11

12 Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!

13

14 Bias Supplies

15 Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!

16 MI8 Excavation

17 Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!

18 Reminder 13.8KV Transformer/Switchgear Replacement - Prepare for next week's transformer/switchgear work - 208V work - Schedule for power outage and switch to generator -0700 to 12:00 for electrical work and switch over to generator Monday March 27 -This will effect BET, BEG and Booster Tunnel