Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1
2
AD & LEIR 27/09/2013 LSC - EN-MEF-OSS 2 AD – BHN06: coils delivered at CERN on 30/10. Test will follow ATRAP area partially dismantled (very good collaboration) – UHM3107 and UVM3207 tanks : removed once again out of the machine for an inspection and the replacement of some gaskets – KFI tanks reinstallation expected mid Oct postponed to November – installation of the new access point is completed LEIR – Sector 1: All equipment back, DHV12 alignment control done, Cooling water restarted – Sector 2: Leak on a flange being repaired, bake-out in place – Access system - In service ATRAP area partially dismantled AD access system LEIR – Sector 2 ready
3
PS Done – New access system doors : SWY hardware installation completed – SMH57: exchange of pumps completed In Progress – CV Consolidation in progress – Consolidation of the 7 PS main magnets started 4 MU have been already removed from beam line and delivered to the Magnet workshop. – Septum 16 External Shielding in progress – Cabling campaign (PS ring) in progress – General equipment maintenance: Instrumentation, Beam Stoppers, (EN/STI) consolidation/maintenance program – PS Tunnel Air leakage sealing project (2 nd /3 phase): Air tightness of wall between TT2 and nTof completed – Power House renovation b355 started 11/10/13 LSC - EN-MEF-OSS3 MU14 removal Air units –center of ring TPS15- MTV cables
4
PSB Completed. – Installation of the new magnet support for the BTY.QFO.108 magnet (beam dump project). – Commissioning of the access control MAD – Successful replacement of the BI.SMH Septum magnet stack In progress – PSB beam dump replacement project on schedule. Reassembly and final survey of the BTM & BTY lines ongoing. – Cooling circuit upgrades to the main bending and quadrupole magnets. – CV consolidation and maintenance, kickers, Septa, vacuum beam instrumentation, Magnet and Beam stopper, cabling campaign. Forecast – Installation of the newly designed BCT’s – Installation of the newly designed Pick ups (UES) – Replacement of the injector line PR137 crane. – Renovation of the machine ring cranes PR134, 135 & 136. 28/08/2013LSC - S. Baird4
5
SPS BA1: – Irradiated cabling campaign in on-going Kicker cables already removed and the installing of the new kicker cables is in progress. TT10: – The new support beams have been installed – Injecting into the crown of the tunnel is now the next step in the process. Other works: – TE/ABT have begun conditioning of the kickers in BA4. – This will continue until the end of November – TE/ABT are in the process of replacing Septas in BA2 – This will continue until the end of the year – EN/CV are replacing blocked pipework in TT20. – On-going – BE/ABP have noticed that the jacks provided for the large quads in sextant 6 are not adapted for the high load and keep on moving…They need to go back again and change them (61710,61810 and 61910) – This will not affect the schedule 20/09/2013LSC - EN-MEF-OSS5
6
Injectors progress curves 11/10/13LSC - EN-MEF-OSS6
7
LHC - P1 R2E – Pt1: – Finished Optical Fiber UJ-UL14/16 Ethernet UJ-UL14 Relocation of cryogenics equipment UJ-UL14 – In progress Commissioning Cryo Relocation of Power Converters UJ-UL14 Cable campaign UJ-UL16 LSS1: – DFBX: consolidation of current leads finished – Cable tray for forward detector finished – 13kA upgrade and displacement of the DQR finished – Modification of the DQR water pipes from next week (emptying) 01/11/13LSC - EN-MEF-OSS7 UL 14 activities
8
LHC – P1 P2 Arc 12 : – Finished SMACC: – W bellows opened – M openings finished and insulation removal – UPS replacement in RE 18 and 22 – In progress SMACC – Shunt installation started – Desolder and Solder BB started DFBA consolidation QRL compensator replacement header D Point 2 – SU maintenance finished – Cryogenic maintenance in progress LSS2 – Consolidation of the DFBX in progress – BTVSI installed – BTVST delayed due to a problem with EB welding machine in AP 01/11/13LSC - EN-MEF-OSS8
9
LHC - P2 P3 Arc 23 – SMACC M opening in progress (32% 82%) – UPS replacement going on in UJ32, finished in RE 28 – QRL Xray campaign in progress – Electrical maintenance P3 completed LSS3 – Cabling campaign Acceptance left side next week Connectors on right side ongoing 01/11/13LSC - EN-MEF-OSS9 UJ32– UPS replacement
10
LHC - P3 P4 Arc 34 – In progress Magnets reconnection completed SMACC: – W bellows completed Cryogenic consolidation completed QRL X-rays – New line C compensator deformed but not leaky P4 electrical maintenance – Forecast SMACC – M openings 01/11/1310 P4 electrical maintenance
11
LHC – P4 P5 LSS4 & P4 – Water cooled cables consolidation finished Short circuit tests next week – Electrical maintenance ongoing – New cooling tower installation in progress – Cryogenic maintenance Arc 45 – In progress QRL pumping Magnet reconnection (end Nov.) » AIV2 tests to be repeted – W opening (65% 85%) – DFBAI.5L – damaged bellow – repair finalized !!!!! – CRG consolidation 01/11/13LSC - EN-MEF-OSS11 DFBAI repairing UX45 - Cryogenic maintenance
12
LHC – P5 LSS5: – TOTEM Cabling finished Piping work postponed week 47 – New walk-ways installation in progress – Forecast New TCLP end mid-November R2E – P5 – Racks installation finished today – Safe room extension in progress – ERD (power converters boards) installation in progress – Relocation safety equipment in progress 01/11/13LSC - EN-MEF-OSS12 UL557 – Racks installation TOTEM cabling
13
LHC – P5 P6 Arc 56 – In progress QRL compensator replaced being tested SMACC – Non conformities being solved – W closure (priority to sector 67 ) – (46% 80%) – 1/14 vacuum subsectors being leak tested (W) » 6 sub-sectors validated DFBA consolidation – 5R – DFBAJ completed – DFBAK.6L – SHM disconnection in progress, transport scheduled on w47 New cables for BLM completed QRL pumping EPC 60A racks re-installation – Forecast UPS replacement 01/11/13LSC - EN-MEF-OSS13 QRL pumping
14
LHC – P6 LSS6 & P6 – Finished Cables pulling – In progress Cables connectors and tests Water cooled cable campaign in progress – priority on DFBAK.6L 600A upgrade TCDQ installed waiting for the TCSP to close beam vacuum Walk-ways installation – Forecast MKB-MKD tests from next week – Issue BPMSB – chlorine traces found on surface – surface bake-out in 2 weeks 01/11/13LSC - EN-MEF-OSS14
15
LHC – P6 P7 Arc 67 – SMACC in progress: Diodes consolidation finished M lines vacuum tests (71% 71%) W Closure activities in progress (32% 70%) 4/14 vacuum subsectors leak tested (W) and 4/14 in progress Beam pipes leak test successful ! DFBA consolidation – 6R DFBAL finished – 7L DFBAM being finalized – QRL compensator finished and tested – BLM new cables installation in progress – Optical fiber from W46 LSS7 – Modification of air ducts finished – 600A upgrade in progress – Consolidation on HRL valves ongoing – Mechanical work on beam vacuum to close A5L7 ongoing – NEG activation of A7R7 next week – No warm magnet transport – in situ consolidation R2E – P7: – Fixation of fireproof racks finished – UPS installation in progress – UTA installation in progress 01/11/1315 Chilled water pipes dismantling being estimated Leak tests
16
LHC - P7 P8 Arc 78 – Splice consolidation in progress Shunt installation completed Insulation boxes installed 22 136/212 M weld 30% Non conformities solving Diodes 67% DFBA consolidation in progress, DFBAO solution under study Ball test performed successfully! 01/11/13LSC - EN-MEF-OSS16 27L8 -bus-bars insulation
17
LHC - P8 LSS8 &P8 – TDI and MCBH removed – BPTX installation tbc – BTVST ready for surface bake-out next week – 2 nd MKI installed next week – Cable campaign ongoing (right side) – Survey with the duct ongoing – NEG activation of I5R8 in 2 weeks – UW maintenance just started R2E - P8 – Shielding installation in US85 in progress 01/11/13LSC - EN-MEF-OSS17 Survey duct P8 US85 shielding installation
18
LHC – arc 81 Arc 81 - SMACC -DFBA consolidation (ends end Nov.) -Splices activities -BB de-soldering completed -BB re-soldering in progress (44% 75%) -Shunt installation (27% 90%) -QRL compensator replaced and tested successfully ! 01/11/13LSC - EN-MEF-OSS18
19
Insulation boxes installation follow-up 01/11/13LSC - EN-MEF-OSS19 Courtesy - M. Pojer
20
Overall progress Injectors – Proposal of Rende being analyzed – Good progress of work LHC – Good progress, but ~3 wks delay SMACC Some co-activities with other activities to organize (optical fibers, electrical maintenance..) – Some issues Electron beam welding machine in AP; TCSP production delay Bus bar insulation boxes… 01/11/13LSC - EN-MEF-OSS20
21
LHC Overall Schedule – broken line 01/11/13LSC - EN-MEF-OSS21