Construction Report July 15, 2008. Projects KMS Phase I TAC Performance Contract Carroll Elementary KMS Phase II –Royalwood / Monahan Elementary –KHS.

Similar presentations


Presentation on theme: "Construction Report July 15, 2008. Projects KMS Phase I TAC Performance Contract Carroll Elementary KMS Phase II –Royalwood / Monahan Elementary –KHS."— Presentation transcript:

1 Construction Report July 15, 2008

2

3 Projects KMS Phase I TAC Performance Contract Carroll Elementary KMS Phase II –Royalwood / Monahan Elementary –KHS Cafeteria –KHS Annex –KMS

4 Projects Middle School #2 Technology –Infrastructure –Phones –LCD projectors –Audio enhancement –District Painting 2008 –District Flooring 2008 –Diamond Sports (pending) –Transportation Complex (pending)

5 KMS Phase I Punch list Close out –Track –Paving –Classrooms

6

7

8

9

10 H. M. Carroll Elementary Final Finishes Punch List

11

12

13

14

15 H.M. Carroll Elementary Landscape Technology Furniture Playground

16

17 Utilities Project (TAC) Punch List Warranty items Close out

18 Middle School #2 Project StartedJanuary 2008 Estimated CompletionAugust 2009

19 Middle School #2

20

21

22

23

24 KMS Phase II Classrooms Labs Entrance Cafeteria/Kitchen Administration area / RR Covered PE Restrooms

25

26

27 KMS Phase II Restrooms Cafeteria Kitchen

28

29

30

31

32

33

34 KMS Phase II Life Skills Classrooms / 2 nd floor

35

36

37

38 Monahan Elementary Entrance Library Clinic Teacher planning rooms Covered PE

39

40

41

42

43

44 Royalwood Elementary Library Classroom renovations Teacher planning rooms Covered PE

45

46

47

48 KHS Cafeteria - started Annex Storage Code compliance / kitchen

49

50

51

52

53 Sheldon 6 Exterior Entrance Classroom renovations Playground Covered PE Track

54

55

56

57

58

59

60

61

62 Painting 2008 (JOC) Diamond sports fields

63

64

65

66

67 District Projects Painting –Royalwood Elem. –Monahan Elem. –KHS Annex –KHS two story

68 District Projects Technology –Audio Enhancement –LCD Projectors –Phones –Infrastructure

69 District Projects Flooring –Monahan Elem. –Royalwood Elem. –KHS Annex –KHS two story –ECA

70 District Projects Air Balance –Sheldon Elem. –ECA –Carroll Elem. –KHS Annex –KHS two story

71 Administration Building Canopies –Pending Doors –In progress

72 KHS / KMS Paving –Pending Fences –Pending Gates –Pending

73 Transportation Complex Property purchased Beltway 8 and Garrett Road

74


Download ppt "Construction Report July 15, 2008. Projects KMS Phase I TAC Performance Contract Carroll Elementary KMS Phase II –Royalwood / Monahan Elementary –KHS."