Presentation is loading. Please wait.

Presentation is loading. Please wait.

TAS-Q1 Status & what if exercise Etude [HL-LHC] TAS-Q1.

Similar presentations


Presentation on theme: "TAS-Q1 Status & what if exercise Etude [HL-LHC] TAS-Q1."— Presentation transcript:

1 TAS-Q1 Status & what if exercise Etude [HL-LHC] TAS-Q1

2 Situation actuelle

3 HiLumi Scénario : Vacuum equipment @ IP side TAS-Q1: bellows+double pump

4 Current HiLumi baseline Equipment @ Machine side Equipment @ IP side  Gate Valve  Angle valves (2)  VAX  BPM  Gate valve + Bellows + Quick flange connectors  BPM (inside Q1 cryostat)… grey position.  Doble pump  Bellows + Quick flange connectors

5 What if… TAS fixed mechanically to Q1?  Bellows  Doble pump + Quick flange connector

6 Concerns  Q1 – structure structural rigidity, support, alignment  Cantilevered weight. 3.2 ton (tas w.o cradle). (Distance to first Q1 support ~4.1 m. Reactions at supports increased 6 to 8 ton+ bending moment --  Angular movement of the front plate. Support would probably need to be displaced towards IP… ( max 0.8 m) If Support @ TAS, no space, no easy alignment, etc,etc.  Vibration modes.  Larger bellows @ IP region

7 Gains  TAS always aligned.  Eliminate need of bellows between TAS @ Q1  No need of TAS alignment system.  If Q1 goes to 22.7 m last 2 BPM’s in green position. Ideally, this could be combined with the elimination of the “new BPM” at IP side: relaxing requirements for alignment, the need of interventions and giving a valuable space in the IP region.

8 8 BPM Position For optimal use during operations, the location of the BPMs should be positioned at least ±60 cm away of the beam crossing points, defined every 3.74m from the IP the “blind areas” Having an BPM that works with collision optics would be important for HL-LHC operation and in particular for luminosity levelling Courtesy P. Fessia Courtesy P. Fessia

9 9 TAS-Q1 Layout proposal for HL-LHC operation A. Maintain the same location of Q1 (L*=23m) and include the Q1-BPM into the cryostat – Allows for fixed mechanical connection between the BPM and the magnet cold mass therefore improved alignment and position monitoring during operations – Mitigates the risk of vacuum leak from the warm BPM of today – We also investigated the option to move Q1 further away from the TAS by ~1m (L*=24m) but doesn’t seem to work penalty for luminosity (small ~5% loss), doesnt’ really solve the access problems, and as all IT magnets would have to move accordingly, puts almost all BPMs of the SS to “blind” positions baseline

10 Page: EDMS No.REV.VALIDITY 10 STUDY BPM POSITION The “blind areas” where shouldn’t be positioned the BPM are located each 3.74m from the IP In this points the beams are crossed so the measurement is not so precise. To avoid this areas we should keep an area of 60cm to each side of those points. SmarTeam: ST0564496_02 BLIND AREAS GOOD AREAS IPIPIPIP

11 Page: EDMS No.REV.VALIDITY 11 C1.R5 C1.R5 “LAY-OUT MACHINE” BPMSQ

12 Page: EDMS No.REV.VALIDITY 12 C2.R 5 BPMSQTBPMSQ “LAY-OUT MACHINE”

13 Page: EDMS No.REV.VALIDITY 13 C3.R 5 BPMSQT “LAY-OUT MACHINE”

14 Page: EDMS No.REV.VALIDITY 14 C4.R 5 BPMSQ “LAY-OUT MACHINE” BPMSQ

15 Page: EDMS No.REV.VALIDITYCONCLUSION Position of the BPM respect to the “blind areas” Moving L*  (-92-242 BMP )= -334mm blind area would be avoided

16 Page: EDMS No.REV.VALIDITY LHC  HL-LHC TAXN Q1 - Flange LHC Sections HL-LHC ?

17 Page: EDMS No.REV.VALIDITY SITUATION CMS CAVERN - LHC START MAGNETIC LENGTH Q1 1300mm ACTUAL START POSITION IN LHC LHC

18 Page: EDMS No.REV.VALIDITY 24000mm IP 5 SITUATION CMS CAVERN - L*24m ACTUAL START POSITION IN LHC START MAGNETIC LENGTH Q1 1300mm LHC HL- LHC

19 Page: EDMS No.REV.VALIDITY 23000mm IP 5 SITUATION CMS CAVERN - L*23m ACTUAL START POSITION IN LHC START MAGNETIC LENGTH Q1 1300mm LHC HL- LHC

20 Page: EDMS No.REV.VALIDITY 22666mm IP 5 SITUATION CMS CAVERN - L*22.7m START MAGNETIC LENGTH Q1 ACTUAL START POSITION IN LHC 1300mm LHC HL- LHC

21 Page: EDMS No.REV.VALIDITY SITUATION ATLAS CAVERN - LHC ACTUAL START POSITION IN LHC 1300mm LHC

22 Page: EDMS No.REV.VALIDITY 24000mm IP 1 SITUATION ATLAS CAVERN - L*24m ACTUAL START POSITION IN LHC 1300mm START MAGNETIC LENGTH Q1 LHC HL- LHC

23 Page: EDMS No.REV.VALIDITY 23000mm IP 1 SITUATION ATLAS CAVERN - L*23m ACTUAL START POSITION IN LHC 1300mm START MAGNETIC LENGTH Q1 LHC HL- LHC

24 Page: EDMS No.REV.VALIDITY 22666mm IP 1 SITUATION ATLAS CAVERN - L*22.7m ACTUAL START POSITION IN LHC 1300mm START MAGNETIC LENGTH Q1 LHC HL- LHC

25  Are the potential gains real? If yes… strong enough to justify work on it?


Download ppt "TAS-Q1 Status & what if exercise Etude [HL-LHC] TAS-Q1."

Similar presentations


Ads by Google