1 University of Calgary Continuing Education
Construction Contract Law and Documents Week 13 Contract Types Forms of Contract

2 Types of Contractual Relations
Design-Bid-Build Stipulated Price Cost Plus Construction Management (CCDC5A) Construction Management at Risk (5B) Design-Build EPC/EPCM Integrated Project Development

3 Standard CCDC/CCA Contracts
CCDC 2 Stipulated Price Contract CCDC 3 Cost Plus Contract CCDC 4 Unit Price Contract CCDC 5A – Construction Management – for services CCDC 5B – Construction Management – for services and construction

4 Standard CCDC/CCA Contracts
CCDC 14 Design-Build Stipulated Price Contract CCDC 15 Design Services Contract between Design-Builder and Consultant CCDC 17 Stipulated Price Contract for Trade Contractors on Construction Management Project Civil Works Project

5 Standard CCA Contract CCA-1 Stipulated Price Subcontract
CCA-19 Stipulated Price Sub- Subcontract

6 Project Documentation
Project budget Your cost – not revenue Enumerate all resource profiles Show all anticipated cost changes (ie: prices)

7 Project Documentation
Project schedule Detailed so that changes in order of work can be identified Show resources on critical activities Show owner supplied deliveries or work Allowance for approvals shown explicitely

8 Project Documentation
Updating Project Plan Critical to ensure credibility (we do this normally – not just to show the error of the other party) Must reflect true activity – don’t try to hide your own dirty laundry Should be accurate record of the plan revisions necessitated by changing conditions

9 Project Documentation
Correspondence Must be formal and organized All formal documentation, initially, should be to the notice address Subsequent, project kickoff meetings would define operational changes to flow of documents – must be confirmed in writing to notice address Separate files for each claim – suggested

10 Project Documentation
Review Contract Note all notice requirements Note notice address No matter what, unless you have a formal instruction, always send Notices to Notice Address Pay particular attention to notices regarding delays, unexpected work, changes to the work – these are the prime source of claims for extras.

11 Project Documentation
Routine Each level of management should review reports from level below Each level of management should prepare material for level above Concept of overlapping and complementary information

12 Project Documentation
Examples Superintendent daily diary (independent corroboration of all site activity – personnel changes, tardiness, everything) Weekly site report by superintendent Perhaps prepared by site engineer by endorsed by site supervisor Reviewed by Project Manager Monthly report by project manager Reviewed by company management.