Presentation is loading. Please wait.

Presentation is loading. Please wait.

TB 14.9.06 Peter Glässel, Heidelberg1 Preparing TPC Installation.

Similar presentations


Presentation on theme: "TB 14.9.06 Peter Glässel, Heidelberg1 Preparing TPC Installation."— Presentation transcript:

1 TB 14.9.06 Peter Glässel, Heidelberg1 Preparing TPC Installation

2 TB 14.9.06 Peter Glässel, Heidelberg2 Preparations in SXL2 Remove clean room wall (towards Muon area) and roof Clear area for trailer Setup hydraulic station DF + TPC DF + TPC

3 TB 14.9.06 Peter Glässel, Heidelberg3 Hydraulic station plan viewside view Alternative: mobile crane

4 TB 14.9.06 Peter Glässel, Heidelberg4 Preparations in UX2 Complete TPC/TRD heat screen Platform under shaft: intermediate support for Delphi Frame (DF) Before L3 magnet Support for DF (surveyed) Space Frame area I-bars stored at BF Connection rails at BSF ITS platform (used when moving TPC)

5 TB 14.9.06 Peter Glässel, Heidelberg5

6 6 Special precautions DF has 4 feet, but no deformation allowed Lifting jig is 3-point 4-point floating hydraulic support 3-point support (on trailer) TPC is a closed volume, safety bubbler with Δp < 1 mbar Watch Δp, ΔT to avoid sucking air CO 2 bottle on DF for replenishing

7 TB 14.9.06 Peter Glässel, Heidelberg7 TPC transport Transport document is prepared DF + TPC: 24 t 1.On SX2 crane from clean room to hydraulic station 2.Raise to allow trailer to pass under DF 3.Lower onto trailer 4.Transport on trailer to SX2 5.Pick-up with hydraulic station 6.Lower to allow transfer to SX2 crane 7.Lower into shaft onto intermediate support 8.Transfer to UX2 crane 9.Move to final support before L3 magnet

8 TB 14.9.06 Peter Glässel, Heidelberg8

9 9 ITS platform Any number of segments possible

10 TB 14.9.06 Peter Glässel, Heidelberg10 Installation sequence Based on previous experience in TPC-ITS integration test 1.Align, install connection rails 2.Move to IP under survey No adjustments of SF during moving foreseen, expected deformations < 2mm (cf. tolerance for beam pipe ±5 mm) 3.Align TPC at IP 4.Move back to ‘parking position’ under survey 5.ITS installation

11 TB 14.9.06 Peter Glässel, Heidelberg11 Spares

12 TB 14.9.06 Peter Glässel, Heidelberg12

13 TB 14.9.06 Peter Glässel, Heidelberg13

14 TB 14.9.06 Peter Glässel, Heidelberg14

15 TB 14.9.06 Peter Glässel, Heidelberg15

16 TB 14.9.06 Peter Glässel, Heidelberg16 Alignment of TPC with Beam Axis Once the TPC is in the final position, the TPC axis is aligned with the beam axis. Again, only the x,y,z, coordinates of the outer (and possibly inner) reference rods on the shaft side can be used to determine the position of the TPC.

17 TB 14.9.06 Peter Glässel, Heidelberg17 Installation of 1 st ITS rail section Two 6m sections of the ITS rails are inserted through the TPC and fixed by the ITS rail fixation points on the frontabsorber. Then, the fixations points are slightly opened to allow the ITS rails to move to the parking position together with the TPC. Since we assume that after movement of TPC to parking position and back to the IP the TPC ends up in the same position, the above procedure will make sure that the ITS rails are well aligned with the TPC when it moves to the IP.

18 TB 14.9.06 Peter Glässel, Heidelberg18 Heatscreen

19 TB 14.9.06 Peter Glässel, Heidelberg19

20 TB 14.9.06 Peter Glässel, Heidelberg20

21 TB 14.9.06 Peter Glässel, Heidelberg21


Download ppt "TB 14.9.06 Peter Glässel, Heidelberg1 Preparing TPC Installation."

Similar presentations


Ads by Google