Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project
3
Activities since last LSC (28/02/2014) Arc splices installation By Activities By sectors SIT DFBA Dashboards Specials Update on overheated splices End of project issue Activities for the next 2 weeks Conclusions
4
JPh Tock 4/29 Sector 56 : Final leak test and reconnection of DFBAK Sector 67 : Complete interventions on NC, reclose insulation vacuum Sector 78 Work on NC, Reconnection of DFBAO-SHM Sector 81 (Priority) Progress on insulation vacuum leak test Sector 12 Complete last IC (#1) Progress on closure of ICs Sector 23 Progress on the installation of electrical insulation Complete Q diodes consolidation Complete M line rewelding (but NCs) Sector 34 Complete installation of electrical insulation Work on overheated splices Start consolidation of Q diodes Sector 45 Complete resoldering of splices Progress on installation of shunts SMACC Main activities for the last 2 weeks >98 % done All shunts are installed > 95% rewelded Resoldering completed DFBAK SHM reconnection on-going [Splices are resoldered], > 98% reclosed, 12/14 vac subsectors leak tested Leaks on K hoses repaired, > ½ is finally LT > 40% done From last LSC (28.02.2014) DFBAK SHM reconnection on-going [Splices are resoldered], Only the last subesector remains to be leak tested Completed > 90% injected and controlled > 75% reclosed >95 % of the shunts are installed Interventions completed, ICs to be reclosed then final LT 1 out of 4 repaired, on-going
5
JPh Tock 5/29 SEQUENCE AND STATUS OK to open Open ICs Install DN200 Open M sleeves ElQC (old splices) Undo / Redo splicesElQC (new splices) Machine Cu > 7.9 sectors ElQC after Cu mach. > 7.9 sectors Install shunts ≈ 7.9 sectors ElQC after shunt ≈ 7.9 sectors Insulate splices ≈ 7 sectors Weld M ≈ 6 sectors Leak test M ≈ 5.5 sectors Close IC > 4.5 sectors Final LT ≈ 3.5 sectors Consolidate Q diodes ≈ 6.5 sectors Cancelled Completed Non-conformities (Before P Test) Non-conformities (After P Test) 1 completed ≈ 3.5 sec-eq Almost completed in 1 st sector (67) Completed
6
JPh Tock 6/29 SMACC Progress report by activity Courtesy H Prin Resoldering: Completed for the whole LHC Some desoldering/resoldering will be necessary because of NC Degradation after Cu machining, non-conformities,… Competence and minimum capacity will be kept up to the end of the project
7
JPh Tock 7/29 SMACC Progress report by activity Cu machining completed in > 7.9 sectors-eq Completed in 3 sectors Only 11 remaining, mostly linked to overheated splices and DFBA SHM reconnection Courtesy MDumas
8
JPh Tock 8/29 SMACC Progress report by activity Shunts are installed in ≈ 7.9 sectors-eq 2 weeks ahead of schedule Saturation effect is seen Completed in 3 sectors (67, 81, 12) Only 16 ICs remains in the whole LHC (≈1%) Shunt weekly installation rate (4 weeks sliding average) *Estimate for W11 Courtesy H Prin
9
JPh Tock 9/29 SMACC Progress report by activity Insulation box: Installed in > 6.5 sectors equivalent Courtesy H Prin / G Maury On the baseline > 3 weeks buffer wrt welding Only 8 ICs left in 6 first sectors (<1 %) but it was 12 ICs 2 weeks ago Issue with some tooling components (mixer), should be solved next week A fall back solution exists (4 weeks sliding average) *Estimate for W8
10
JPh Tock 10/29 SMACC Progress report by activity Consolidation of Q Diodes: in ≈ 6.5 sectors equivalent Detailed schedule worked out Should not interfere with welding activities NC of un~/badly coated BB Already decided to “use as is” if on magnet side Decision extended to diode side [Diodes WG 26.02.2014] was confirmed at TETM 11.03.2014 Courtesy L Grand-Clement,
11
JPh Tock 11/29 SMACC Progress report by activity M Welding : Done in ≈ 6 sec-eq: Routinely 60 ICs/week Work concentrated in 1 sector, starting in 34 (7 th /8) No major disturbance Exactly on the baseline presented on 4.10.2013 Detailed presentation at next LSC As presented LSC 4.10.2013 11 weeks @ 34 18 weeks @ 51 Slightly ahead of revised schedule Courtesy S Atieh
12
JPh Tock 12/29 SMACC Progress report by activity M sleeves leak testing : Completed in ≈ 5.5 sec-eq Following the M lines rewelding, less regular by nature (sectorization) ≈ 3 weeks behind schedule Under recovery as for the M welding Courtesy P Cruikshank / L Mourier
13
JPh Tock 13/29 SMACC Progress report by activity Reclosure of interconnections : > 4.5 sec equivalent are reclosed Work mainly in S12 and starting in S23 On the baseline The 1000 th IC will be closed this afternoon Courtesy A Chrul / A Musso
14
JPh Tock 14/29 SMACC Progress report by activity Final leak test: > 750 ICs validated, > 3.5 sec equivalent 3 weeks to have results after repumping S56: only DFBAK subsector remains S67: fully validated but subsectors to be revalidated after interventions on NC S78: 12 subsectors validated S81: 11 subsectors validated, 3 under test, several interventions S12: 6 subsectors under test About 1 week behind schedule, was 3 weeks at last LSC
15
JPh Tock 15/29 SMACC Sector 67 2 leaks fixed, one not localised, accepted as is On-going: Reclosure and final leak test of insulationvacuum SMACC Sector 81 Remaining : Less than half of W leak test and DN200 (Back on baseline )
16
JPh Tock 16/29 SMACC Progress report by sector Main activities are : Leak test of M lines Closure of interconnections 6/14 subsectors are under final LT Main activities are : Welding of M lines Leak test of M lines Start reclosure of Ics (Today)
17
JPh Tock 17/29 SMACC Progress report by sector Main activities are : Work on overheated splices (More info in next slides) Q diodes consolidation Rewelding of M lines Main activities are : Installation of shunts Installation of electrical insulation
18
JPh Tock 18/29 SMACC Dashboards Shunting is slowing down (Difficult cases: overheated splices, DFBAs,… ) The installation of insulation boxes is ahead of the baseline Welding and M leak test rates are recovering the baseline schedule in parallel Reclosure: On baseline, nominal rate achieved Insulation vacuum leak test : RECOVERING Disturbances of leak tests (M lines and insulation vacuum) have to be minimised
19
Completed New
20
JPh Tock 20/29 SMACC Progress report SIT SIT Team is reduced but can be remobilised very quickly Activities linked to NC, leaks and overheated splices Courtesy N Bourcey, S Le Naour
21
JPh Tock 21/29 SMACC DFBA Courtesy A Perin, E Vergara 95% of splices are consolidated OK for just in time (New schedule) Many operations are well advanced but not completed 8 DFBAs are completed
22
JPh Tock 22/29 SMACC Dashboards Baseline:82.7 % (77.4 %) Completed:84.2 % (78.9 %) Delay -3 (-3) days Baseline:76.9 % (72.8 %) Completed:74.9 % (69.0 %) Delay 10 (20) days Ahead of schedule Decreasing delay Arc splices: Stable but difficult cases ahead SIT Delay decreases, waiting validation DFBA: Many activities on-going In the shadow of the arcs Baseline:85.7 % (81.1 %) Completed:67.1 % (57.4 %) Delay 3 (4) months Recovering
23
JPh Tock 23/29 SMACC Dashboards Progress: Baseline:82.5% (77.5 %) Completed:82.1% (76.6 %) Delay2 (6) days Decreasing ; Δbaseline <≈ Δcompleted
24
JPh Tock 24/29 SMACC Overheated splices From LSC of 07.02.2014 9 Courtesy C Scheuerlein, F Savary 5 1 6 Confirmed as is Within the present schedule, possible to repair 4 to 5 splices with new cables [Forecast is max 6]
25
JPh Tock 25/29 End of project issue Courtesy R Ostojic, M Struik In order to alleviate effect of the end of work atmosphere, presence in the tunnel is increased: * One extra staff (Thx TE-VSC) to second worksite supervisors * Auditors are reinforced and are intensifying audits
26
JPh Tock 26/29 SMACC Summary on progress Main 13 kA Splices: On schedule Q Diodes consolidation : Almost all components are at CERN and tested Overheated splices : to be followed up closely Leak test rate is according to forecast, slightly more needed Special Interventions: Delay is decreasinng Almost all planned interventions are completed Focus on NC DFBA: Activities are back in the shadow of arc splices (except 56-78) SMACC: About 2 days of delay, reducing wrt schedule defined one year ago !! Very slightly more than nominal rate achieved these last 24 weeks !
27
JPh Tock 27/29 Sector 56 : Final leak test and reconnection of DFBAK Sector 67 : Reclose insulation vacuum and start final leak tests Sector 78 Work on NC Reconnection of DFBAO-SHM Sector 81 (Priority) Complete insulation vacuum leak test Sector 12 (Priority) Reclose last ICs Progress on insulation vacuum leak test Sector 23 Complete the installation of electrical insulation Complete M line rewelding (but NCs) Progress on M-lines leak testing Start reclosure of ICs Sector 34 Work on overheated splices Complete consolidation of Q diodes Sector 45 Progress on installation of shunts Progress on electrical insulation SMACC Main activities for the next 2 weeks
28
JPh Tock 28/29 Conclusions Project is almost back on schedule (-2 days) Mind the last X % effect Leak testing is reaching the planned rates DFBA consolidation is progressing very well Overheated splices : On the critical path S67 is almost ready for next step (ElQA before cooldown foreseen end of April) S81 should be ready on time for pressure test (8.04.2014)
29
JPh Tock 29/29 Advancement is > 80 % …. But
31
JPh Tock 31/29