R2E Mitigation Project Status Report 2 nd R2E Committee Meeting 20.01.20111R2E Project Report.

Similar presentations


Presentation on theme: "R2E Mitigation Project Status Report 2 nd R2E Committee Meeting 20.01.20111R2E Project Report."— Presentation transcript:

1 R2E Mitigation Project Status Report 2 nd R2E Committee Meeting 20.01.20111R2E Project Report

2 Follow-Ups R2E Mandate: not required for Chamonix presentation, propose however that we reorganize the website according to committee and project (according to current understanding) Safe-Rooms: phased approach agreed upon -> see last slide “Benchmarking”: -> see report from Marco Layout drawings: 90% ready, whom to contact to include them into the official repository Memorandum for P5: update from RP + safe room discussion to be included -> rather a report than a memorandum? 20.01.20112R2E Project Report

3 R2E Highlights (Dec, Jan) Detailed Analysis of 2010 Operation – RadMon, BLM & Ratios – TLD Results for low-rad readings – Analysis of losses/luminosities/intensities Shielding & Integration – P5 close to baseline (few issues: e.g., support structure) – Opening of shielding tender (21.1.) – Shielding update for US85 – P1 issue through UX/UL wall Power-Converter R&D – Project advancing (conceptual studies) – 1 st course on radiation hard developments held (for TE/EPC) – Extensive component test campaign for 2011 (test request?) – Collaboration set up with University of Montpellier & TRAD Safe-Rooms – phased approach developed together with EN/EL (waiting for safety input for phase-I, EN/EL for phase-II/III) – Critical point for baseline in P5 and P7 Benchmarking (good agreements with FLUKA) – UX85/US85 – IR7 + … 20.01.20113R2E Project Report Calibration, Calibration, Calibration Priority: Ready for 2012

4 Safe-Room Update phased relocation approach which foresees: a first relocation of the most sensitive control equipment (racks: EYU, EYC and EYP) 230/48V supply from the surface (safety light + remaining 48V equipments) AUG verification and options (surface or other location) relocation of remaining (so-far judged low- risk) equipment, especially in case new (sensitive) components have to replace the existing equipment 20.01.20114R2E Project Report Reduce Risk Improve If Required Radiation Tests in H4

5 Further Failure Rate 2010 Radiation Level Analysis Update of Estimate (scary) Interesting Loss balance not available (so far) by OP Many issues with quality of logging (and signals) -> difficult for anlaysis Aiming for 50ns in 2012 (~100MJ or 1/2nom @4TeV) 20.01.20115R2E Project Report See Chamonix Slides

6 R2E Global Strategy & Dates 20.01.20116R2E Project Report Study Phase (2008-2010) Calculations, Early Actions, Strategy Study Phase (2008-2010) Calculations, Early Actions, Strategy Project Proposal (2010) Testing, Evaluation, Mitigation Plan Project Proposal (2010) Testing, Evaluation, Mitigation Plan R2E Mitigation Project (2011-2016) Medium Term R&D For Long-Term EvaluationEvaluationLong-TermLong-Term Shielding & Relocation P1, P5, P7, P8 (+ small items) Shielding & Relocation P1, P5, P7, P8 (+ small items) PanicPanicEvaluationEvaluation StrugglingStruggling ResourcesResources Power- Converters Rad-Tol Solution SCLs Horizontal/ Vertical Links Power- Converters Rad-Tol Solution SCLs Horizontal/ Vertical Links Monitoring Analysis, Calibration Testing Component & System Tests Monitoring Analysis, Calibration Testing Component & System Tests CombinationRelocation Rad-Tol Equipment SCLs (Civil Engineering) CombinationRelocation Rad-Tol Equipment SCLs (Civil Engineering) Key Dates (Status 01.2011): 02.11. (Cables) 03.11. (SafeRoom1) 06.11. (SafeRoom2) 11.11. (1 st Test Results) 12.11. (1 st CD Review) 2012 (FGCs Production) 2010 Operation 06.11 (UX/UL@P1) 08.11. (CE Prestudy) 04.12 (CE Study) 10.12. (Hori-SCLs) 2013 (PCs and/or SCLs)


Download ppt "R2E Mitigation Project Status Report 2 nd R2E Committee Meeting 20.01.20111R2E Project Report."