Pink Elephant Showcase - 21.12.2015 1
2
Brief What have we done last week? o Deliverables o Milestone Progress o Estimations What are we going to do this week? o Deliverables of the Final Week Pink Elephant Demo 2
3
Deliverables Project Plan - Rev 1.8 RSD - Rev 1.6 DSD - Rev 1.1 M8 - Search Software Product Manual - Rev 1.2 Project Demo o Mobile o Web 3
4
Test Cases 4 45 issues in web project 5 issues in mobile project
5
More Accurate Project Plan 5
6
Revisions of Repository Main Pages 6 Brief information is given Wiki page redirection
7
Semantic Search Implementation with DBPedia Integration 7 Label and context Tag recommendation based on DBPedia
8
Bugfixing and Uncomplete Issues 8
9
Milestone Progress M8 - Search (including Search functions + bugfixes + uncomplete issues) Web Project o 36 % complete o 52 open, 30 closed o 53 bug issues Backend Services Project o 80 % complete o 13 open, 54 closed o 17 bug issues Mobile Project o 67 % complete o 10 open, 21 closed o 19 bug issues 9
10
Estimations Barı ş Özcanlı 10 IssueEstimationActual Coding & Bugfixing 8 hours 1 hour Communication1 hour0,5 hours Total9 hours1,5 hours
11
Estimations Hayri Can Akyel 11 IssueEstimationActual Coding2 hours- Issue Tracking8 hours7 hours Test Cases & Testing 5 hours6 hours Documentation5 hours6 hours Creating Mockup Data on Web -0,5 hours Communication1 hour Total21 hours20,5 hours
12
Estimations Mehmet Çelikel 12 IssueEstimationActual #245 Contact Person Details (Meeting) 1 hour #244 DBPedia Integration 10 hours14 hours #247, #246 Bugfixing1 hour Communication1 hour Total13 hours17 hours
13
Estimations Orkun Koçyi ğ it 13 IssueEstimationActual Implementing Tagging System 2 hours3 hours Implementing New Requests 1 hour1.5 hours Redesigning Models1 hour Issue/Bug Fixing1.5 hour Redesigning Layouts2 hours Communication1.5 hour Total9 hours10.5 hours
14
Estimations Recep Günay 14 IssueEstimationActual Coding and Bugfixing 10 hours12 hours Communication1 hour Total11 hours13 hours
15
Estimations Sinan Can Sürücü 15 IssueEstimationActual Messaging Function Development 8 hours6 hours Messaging Function Testing&Bugfixing 2 hours1 hour Search Function Development 3 hours Search Function Testing & Bugfixing 1 hour Bugfixing3 hours4 hours Communication1 hour Total 18 hours16 hours
16
Estimations 16 EstimationActual Coding & Bugfixing56,5 hours53 hours Communication6,5 hours6 hours Issue Tracking8 hours7 hours Documentation10 hours12,5 hours Total 81 hours78,5 hours
17
Deliverables of Final Week Project Plan Rev 1.9 Software Product Manual Rev 1.3 M9 Final Release Project Demo o Mobile o Web 17
18
Thank you! 18 We will continue to the showcase with product demo.