Division 1 – General Requirements Review Questions
2
1.Section 011100- Summary of Work— specifies administrative details and responsibilities of the: a.A/E b.Owner and A/E c.Contractor and Subcontractor d.None of the above
3
1. Section 011100 – Summary of Work-- specifies administrative details and responsibilities of the: a.A/E b.Owner and A/E c.Contractor and Subcontractor d.None of the above
4
2.Administrative provision of the construction contract are: a.Fully specified in the Conditions of the Contract b.The Contractor’s responsibility and should not be specified c.Written in Division 1 to expand on provision in the Conditions of the Contract d.Written in a manner to avoid Owner responsibilities.
5
2.Administrative provision of the construction contract are: a.Fully specified in the Conditions of the Contract b.The Contractor’s responsibility and should not be specified c.Written in Division 1 to expand on provision in the Conditions of the Contract d.Written in a manner to avoid Owner responsibilities.
6
3.Division 1 sections specify: a.Administrative requirements, procedural matters, and temporary construction facilities b.Legal requirements that would not normally be included in standard General Conditions c.Special Conditions of the Contract
7
3.Division 1 sections specify: a.Administrative requirements, procedural matters, and temporary construction facilities b.Legal requirements that would not normally be included in standard General Conditions c.Special Conditions of the Contract
8
4.Which is true regarding the Drawings? a.Have no direct relationship to Division 1 of the specifications b.Need not be coordinated with Division 1 c.Graphically define certain subject matter specified in Division 1, such as “Scope of Work” d.May define related work that may or may not be part of Contract e.Provide the coordination between administrative sections of Division 1 f.Both c and d
9
4.Which is true regarding the Drawings? a.Have no direct relationship to Division 1 of the specifications b.Need not be coordinated with Division 1 c.Graphically define certain subject matter specified in Division 1, such as “Scope of Work” d.May define related work that may or may not be part of Contract e.Provide the coordination between administrative sections of Division 1 f.Both c and d
10
5.Owner occupancy of the premises during construction: a.Should not be specified in section covering temporary facilities b.Is specified in Section 011100 – Summary of Work c.Is not a concern of the specifier d.Precludes Contractor’s use of existing facilities such as stair’s, elevators, and sanitary facilities
11
5.Owner occupancy of the premises during construction: a.Should not be specified in section covering temporary facilities b.Is specified in Section 01110 – Summary of Work c.Is not a concern of the specifier d.Precludes Contractor’s use of existing facilities such as stair’s, elevators, and sanitary facilities
12
6.Which of the following items should not be included in Section 011100? a.Owner-furnished items of work b.Site traffic regulations during construction c.Sequence of work and Owner occupancy d.Contractor’s use of site
13
6.Which of the following items should not be included in Section 01110? a.Owner-furnished items of work b.Site traffic regulations during construction c.Sequence of work and Owner occupancy d.Contractor’s use of site
14
7.Submittal requirements for Mechanical and Electrical work are specified in: a.General Conditions b.Supplementary Conditions c.Division 1 d.Divisions 15 and 16
15
7.Submittal requirements for Mechanical and Electrical work are specified in: a.General Conditions b.Supplementary Conditions c.Division 1 d.Divisions 15 and 16
16
8.Division 1 sections: a.Cover general requirements for execution of the work, and must be written in broad language b.Reinforce the concept “say it once” by stating procedural matters only once c.Should be bound in a separate volume of the Project Manual d.Both a and b
17
8.Division 1 sections: a.Cover general requirements for execution of the work, and must be written in broad language b.Reinforce the concept “say it once” by stating procedural matters only once c.Should be bound in a separate volume of the Project Manual d.Both a and b
18
9.Bidding Requirements: a.Are not enforceable during administration of contract b.Should not repeat Division 1 c.Should be referenced to the General Conditions d.Bear no relationship to the Contract Documents e.Both a and b
19
9.Bidding Requirements: a.Are not enforceable during administration of contract b.Should not repeat Division 1 c.Should be referenced to the General Conditions d.Bear no relationship to the Contract Documents e.Both a and b
20
10.Provisions in the Conditions of the Contract: a.Have priority over Division 1 b.Are superseded by Division 1 c.Are expanded by the provisions of Division1 d.Are independent and Division 1 provisions have no effect
21
10.Provisions in the Conditions of the Contract: a.Have priority over Division 1 b.Are superseded by Division 1 c.Are expanded by the provisions of Division1 d.Are independent and Division 1 provisions have no effect
22
11.Which statements are true concerning Supplementary Conditions: a.They should not contain general references to Division 1 b.They should be used to expand and modify basic provision stated in the General Conditions c.a only d.Both a and b
23
11.Which statements are true concerning Supplementary Conditions: a.They should not contain general references to Division 1 b.They should be used to expand and modify basic provision stated in the General Conditions c.a only d.Both a and b
24
Answers 1.dd 2.cc 3.aa 4.ff 5.bb 6.bb 7.cc 8.dd 9.ee 10.cc 11.dd