1
1 Project Plan Review Ashley Brawner Neelam Datta Xing Huang Jesse Jones AAE451: Team 2 Matt Negilski Mike Palumbo Chris Selby Tara Trafton
2
2 Task Assignments Aerodynamics Jesse Jones Chris Selby Structures & Weights Matt Negilski Neelam Datta Propulsion Xing Huang Mike Palumbo Dynamics & Control Ashley Brawner Tara Trafton Team Leader: Co-Leader: Meeting Planners: Matt Negilski Jesse Jones Xing Huang & Ashley Brawner
3
3 Officer Responsibilities Team Leader (Matt) Send reminder emails Keep team on schedule Co-Leader (Jesse) Assist team leader Keep contact list Meeting Planners (Ashley & Xing) Reserve team meeting location Assist in reserving locations for the different panels
4
4 Team Meetings Regular Team Meetings When: Every Thursday @ 7:00pm Where: Grissom 274 (subject to change) Individual Group Meetings When: 1 or 2 days before any major deliverable (PDR/QDR) Where: Choice of the individuals
5
5 Project Schedule Gantt Chart format Easy interpretation Concise Project break-down Design Build Test Finalize
6
6 Gantt Chart: Design Phase 1 Legend Green = Team Work Blue = Aero Work Red = Propulsion Work Black = Structures Work Purple = D&C Work ♦ = Milestones
7
7 Gantt Chart: Design Phase 2 Legend Green = Team Work Blue = Aero Work Red = Propulsion Work Black = Structures Work Purple = D&C Work ♦ = Milestones
8
8 Gantt Chart: Build/Test Phase Legend Green = Team Work Blue = Aero Work Red = Propulsion Work Black = Structures Work Purple = D&C Work ♦ = Milestones
9
9 Gantt Chart: Finalize Project Legend Green = Team Work Blue = Aero Work Red = Propulsion Work Black = Structures Work Purple = D&C Work ♦ = Milestones
10
10 Major Milestones Engine Selection (10/17) Parts Ordered (10/19) Design Frozen (10/26) Flight Readiness Review (11/16)
11
11 Questions?