1
Yingchao ZHAO, Caritas Institute of Higher Education Xiangtong QI, HKUST Minming LI, City University of Hong Kong
2
Traditional scheduling objective ◦ minimizing makespan ◦ minimizing total completion time ◦ minimizing total flow time. Wan and Qi (Naval Research Logistics) proposed the model that considers both traditional objective and time slot cost. Kulkarni and Munagala (WAOA 2012)studied online algorithms to minimize the total weighted completion time plus time slot costs. Leonardi et al. (MAPSP 2013) designed a PTAS for the offline version of the problem.
3
Increasing ◦ Trivial ◦ Execute the jobs as early as possible Decreasing ◦ Linear decreasing ◦ Accelerative decreasing ◦ Decelerative decreasing ◦ General decreasing Objective ◦ Minimize: total weighted completion time + time slot costs
4
π(t) t
5
For each job i: ◦ Processing time p i ◦ Weight w i The time slot cost π satisfies π k - π k+1 =ε, ε>0 We give a polynomial time algorithm to get the optimal schedule for this problem. ◦ Given two jobs, which should be processed earlier? ◦ Given a job, when should it be processed?
6
If the time slot cost decreases as a linear function with respect to time k, then there exists an optimal schedule to the problem in which jobs are scheduled in WSPT (Weighted Shortest Processing Time) order.
7
For a job with processing time p and weight w If w/p>ε, process this job as early as possible If w/p<ε, process this job as late as possible If w/p=ε, the job has the same cost no matter when it is processed
8
t 0K 0 t K t K0w/p>εw/p<εw/p=ε Sort the jobs according to decreasing w/p. Partition jobs into three sets: J 1, J 2, J 3 Process J 1 and J 2 from time zero, and process J 3 as late as possible. Solved in polynomial time!
9
π(t) t
10
The time slot cost π satisfies π k - π k+1 > π k-1 - π k, for 1<k<K For each job ◦ Processing time p ◦ Weight w ◦ Worst starting time k’, π k’+1 - π k’+p+1 > w > π k’ - π k’+p There is only one possible idle time interval in an optimal schedule. Every job has a worst starting time
11
If a job starts before its worst starting time k’, then there is no idle time before it in the optimal schedule. If a job starts after its worst starting time k’, then there is no idle time after it in the optimal schedule. If a job starts at its worst starting time k’, then there is no idle time before and after it in the optimal schedule. k’ 0 K
12
In an optimal schedule, the jobs are partitioned into two parts. ◦ The first part starts from time zero. ◦ The second part ends at time K. In each part, jobs are processed in WSPT order. 0K How to partition jobs?
13
0xy Where is job m? Job m is in the last job of in the first part Job m is in the last job of in the second part jobs in the same part are scheduled in WSPT order f(m,x,y) denotes the minimum cost for jobs 1 to m, where the first part ends at x, and the second part starts at y. need to know f(m-1, x-p m, y) need to know f(m-1, x, y) O(nP 2 )
14
π(t) t
15
The time slot cost π satisfies π k - π k+1 < π k-1 - π k, for 1<k<K For each job ◦ Processing time p ◦ Weight w ◦ Preferred starting time: k*, π k*+1 – π k*+p+1 > w > π k* - π k*+p ◦ Preferred processing interval: [k*, k*+p]
16
k* k*+p 0 K If a job starts before its preferred starting time k*, the earlier it is processed, the more cost it will have. If a job starts after its preferred starting time k*, the later it is processed, the more cost it will have. If a job starts at its preferred starting time k*, it will have the least possible cost.
17
Job i Job j If two jobs’ preferred processing intervals have no overlap, then the job with earlier preferred starting time has greater ratio of w/p than the other job. w i /p i w j /p j > If two jobs’ preferred processing intervals have overlap, but not completely contain each other, then the job with earlier preferred starting time has greater ratio of w/p than the other job. Job i Job j w i /p i w j /p j >
18
The jobs are scheduled in WSPT order in the optimal solution. If two jobs are adjacent in WSPT order and their preferred processing intervals have overlap, then there exists no idle time slot between these two jobs in the optimal solution. Job i Job j (w i, p i) (w j, p j ) Job i’ (w i + w j, p i +p j ) Algorithm: 1.sort by WSPT 2.merge and replace 3.assign to preferred intervals O(n 2 )
19
π(t) t
20
Theorem 1. The problem with arbitrary non- increasing time slot cost is NP-hard in the strong sense. 3-Partition Instance: n=3q integers a 1, a 2, …, a 3q integer b with b/4<a j <b/2 sum(a j )=q*b Scheduling Instance: n=3q jobs processing time a j, weight ε*a j K=q(b+1)
21
Polynomial time algorithm for the accelerative decreasing case More classes of decreasing cost Other objectives besides total weighted completion time Multiprocessor
22
J. Kulkarni and K. Munagala, Algorithms for cost aware scheduling, in Proceedings of 10th International Workshop on Approximation and Online Algorithms (WAOA 2012), 201-214. S. Leonardi, N. Megow, R. Rischke, L. Stougie, C. Swamy and J. Verschae, Scheduling with time-varying cost: deterministic and stochastic models, in 11th Workshop on Models and Algorithms for Planning and Scheduling Problems (MAPSP 2013). G. Wan and X. Qi, Scheduling with variable time slot costs, Naval Research Logistics, 57 (2010) 159-171.