CMCSS Elementary School 20 year plan
2
Montgomery County Civil Districts
Objectives: Establish zoning corridors throughout the county for the purpose of long range forecasting of facility needs Tie CMCSS student data to Planning commission growth data Allow sharing of most recent data between governmental entities Existing Civil Districts based on census tracts used by Planning Commission for projections 1
3
CMCSS Middle/High Feeder Systems
Rossview St B./Burt RoMS RHS Sango Northeast Barkers Mill NEMS NEHS Glenellen Hazelwood Northeast Kenwood Kenwood KMS KHS Ringgold B. Darden Northwest/New Prov. Woodlawn NPMS NWHS Liberty Minglewood Clarksville/Richview Barksdale RiMS CHS E.Mont. Moore N.Smith Mont. Central Cumb. Hts. MCMS MCHS Central 6 Mid/High Feeder Systems Northeast Rossview Kenwood New Providence/ Northwest Richview/ Clarksville Montgomery Central 2
4
CMCSS Zoning Regions Region 2 Region 1 Region 3 Region 4 Region 5
Combination of 21 Civil Districts and 5 Mid/High Feeder Systems Region 1 St B./Burt RoMS RHS Sango Region 2 Barkers Mill KMS KHS Glenellen NEMS NEHS Hazelwood Kenwood Northeast Ringgold B. Darden Region 3 Woodlawn NPMS NWHS Liberty Minglewood Region 4 Barksdale RiMS CHS E.Mont. Moore N.Smith Region 5 Cumb. Hts. MCMS MCHS Central Region 2 Region 1 Region 3 Region 4 Region 5 3
5
Elementary Building Capacity/Student Enrollment
Table Based on October 2006 Capacity and Enrollment 4
6
Zoning Region Capacity and Enrollment Over Time
Elementary Capacity Zoning Region Capacity and Enrollment Over Time Analysis from 1998 to 2026 Ave. Growth Rate = 43 Summary: Open Rossview : 2009 5
7
Zoning Region Capacity and Enrollment Over Time
Elementary Capacity Zoning Region Capacity and Enrollment Over Time Analysis from 1998 to 2026 Ave. Growth Rate = 191 Summary: Open West Creek : 2008 Purchase Land in Region Open New Elem.: 2013 6
8
Zoning Region Capacity and Enrollment Over Time
Elementary Capacity Zoning Region Capacity and Enrollment Over Time Analysis from 1998 to 2026 Ave. Growth Rate = 9 Summary: Open Lafayette : 2021 7
9
Zoning Region Capacity and Enrollment Over Time
Elementary Capacity Zoning Region Capacity and Enrollment Over Time Analysis from 1998 to 2026 Ave. Growth Rate = 93 Summary: Purchase Land in Region Open New Elem.: 2011 8
10
Zoning Region Capacity and Enrollment Over Time
Elementary Capacity Zoning Region Capacity and Enrollment Over Time Analysis from 1998 to 2026 Ave. Growth Rate = 15 Summary: Purchase Land in Region Open New Elem.: 2023 9
11
Elementary School Construction
20 Year Plan (Based on Linear Enrollment Projection) Region Capacity Break Point New Elementary Opening @ West Creek @ Rossview * * * * @ Lafayette * * Requiring New Site 10