NEXT BEAM INSTALLATION MASSDOT BRIDGE REPLACEMENT ROUTE 19 OVER MILL BROOK BRIMFIELD E.T.& L. CORP.
2
NEXT BEAMS Quantity ~ 6 beams Length ~ 67 ‘ Width ~ 8’ Weight ~ 82,422 lb E.T.& L. CORP.
3
Minimal deck formwork Ease of erection Reduced construction time Increased jobsite safety E.T.& L. CORP.
4
Weight of Beams Two Cranes Unloading Area E.T.& L. CORP.
5
Beam camber movement during concrete deck placement Minimal adjustment for top of final deck elevation E.T.& L. CORP.
6
Concrete clearance 6” Stirrups Overhang bracket clips Bidwell Setup E.T.& L. CORP.
7
QUESTIONS / COMMENTS E.T.& L. CORP.