Gas system for NA62 Straw detector Roberto Guida On behalf of Gas Service Team NA62 Straw working meeting, March 26, 2012 Outline: P&I Drawing Schedule Distribution racks Mixer and control racks Conclusions
2
P&I drawing
3
Construction schedule Key dates: -All racks ready for beginning June -Installation during July/August -Test/commissioning beginning September
4
Gas distribution racks - Gas distribution is made using Festo pneumatic units controlled through profibus - System tested for ageing in TRT test set-up - All material received - Construction of distribution racks is started Check/finalize length and routing of last capillary pipe on the chambers to be discussed
5
Mixer and Control racks - Mixer and Control racks are in a early stage of construction - 70% of material for Mixer is arrived - For Control rack layout we are waiting few inputs on PLC and interfaces choices - 24 V power supplies to be ordered - We expect to fix these points this week MixerControl rack
6
Conclusions The construction of the gas system for the NA62 Straw detector is on going Gas distribution racks are a bit more advanced mixer and control racks are still on-schedule URD for the software controls definition is started and it will be send to EN in 1-2 weeks Software controls (EN) expected to be read beginning September Review/Update of the status in about 2 months (when all racks should be almost ready) Budget status Used about 60% of allocated budget Mainly for materials.