Federal Aviation Administration System Wide Information Management SWIM Implementing Programs (SIPs) Status Presented to: Demonstrations and Prototypes TIM 5 Presented by: Jeffery L. Hobbs Date: May 26, 2010
2
2 Federal Aviation Administration Presented to: Demonstrations and Prototypes TIM 5 Date: May 26, 2010 Aeronautical Information Management (AIM) Operational Repository Deployment is planned for July 7, 2010 Static Repository Deployment is Planned for June 28, 2010 Editor Deployment is TBD –OKC site location pending Initial Operating Capability is Tentatively Planned for September 13, 2010
3
3 Federal Aviation Administration Presented to: Demonstrations and Prototypes TIM 5 Date: May 26, 2010 Traffic Flow Management (TFM) Reroute Service (R5) –Early Developer Testing with ERAM Continues in June 2010 –Additional Development Continues –Deployment Planned for April 2011 Flow Publication Service (R7) –Requirements Complete –Early Prototyping –High Level Design in Process
4
4 Federal Aviation Administration Presented to: Demonstrations and Prototypes TIM 5 Date: May 26, 2010 En Route Automation Modernization (ERAM) Phase 1 (Reroute/R3) Key Site TBD Phase 1 Developer Testing with TFM Ongoing Completed 16 of 18 Iterations of Phase 1 Phase 2 Hardware Evaluation ongoing –Number of Sites –Storage Requirements –Performance Requirements –Security Requirements
5
5 Federal Aviation Administration Presented to: Demonstrations and Prototypes TIM 5 Date: May 26, 2010 Corridor Integrated Weather Service (CIWS) CIWS Prototype Operational with 5 products –Client Package (User guide, CIWS Product Report, and Client software) Developed and Provided to Users –Signed MOAs with Delta Airlines, Raytheon Company, ARINC, Harris Corporation, Kent State University, and WSI Corporation CIWS Capability Software under Development –Enhanced Monitoring Software Completed –Additional 10 Products will Included in Capability CIWS Capability Operational September, 2010
6
6 Federal Aviation Administration Presented to: Demonstrations and Prototypes TIM 5 Date: May 26, 2010 Weather Message Switching Center Replacement (WMSCR) Connected to FTI National Test Bed Completed SAT Procedures Designed Circuit Monitoring and in Process of Implementation IOC planned for June 2011
7
7 Federal Aviation Administration Presented to: Demonstrations and Prototypes TIM 5 Date: May 26, 2010 Integrated Terminal Weather System (ITWS) ITWS Prototype Operational began on October 6, 2008 with 4 products –UPS, Harris, DoD, and FedEx, NWA have Signed MOAs –UPS, Harris, DoD, and FedEx are Receiving Data –31 Products currently now Available Refining ITWS Capability –Capability Planned to be Operational January 2011
8
8 Federal Aviation Administration Presented to: Demonstrations and Prototypes TIM 5 Date: May 26, 2010 Terminal Data Distribution System (TDDS) Completed Proof of Concept Started Prototype Development Requirements Development in Process Started Safety Process for Capability Capability Planned to be Operational May 2013
9
9 Federal Aviation Administration Presented to: Demonstrations and Prototypes TIM 5 Date: May 26, 2010 SWIM Implementation Registry/Repository contract awarded to HP for Systinet on April 27, 2010 Registry/Repository will be operational on Administrative LAN at the WJHTC on July 1, 2010 Revision to the XML QVL in process