Tollway Barrier Guidelines Examples Hands-On Workshop III July 2013 1
2
Each AOC should be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runoutm. Upstream End of Barrier Wall e. Shy Line Offsetn. Downstream Terminal f. Foreslope / Backslopeo. Barrier Obstacle g. Clear Zonep. Compare existing length to proposed h. Clear Zone Adjustmentq. Prepare warrant text and exhibits i. Lateral Extent of the Area of Concern 2
3
Level 2 Example- Location 9 3
4
4
5
Each AOC shall be analyzed separately. a. Establish EOTW 5
6
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed 6
7
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT 7
8
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout 8
9
L2L2 Figure 5-39. Approach Barrier Layout Variables LRLR 9
10
Level 2 Example- Location 9 10
11
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset 11
12
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope 12
13
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone 13
14
g. Clear Zone Select highest value in range Table 3-1 Clear Zone Distances in Feet from EOTW 14
15
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment 15
16
h. Clear Zone Adjustment 16
17
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 17
18
i. Lateral Extent of the Area of Concern L2L2 Figure 5-39. Approach Barrier Layout Variables LALA 18
19
Level 2 Example- Location 9 Lateral Extent of the Area of Concern L A = L A = 23.9’ + 1.5’ = 25.4’ 19
20
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 20
21
Flowchart for Analysis of Existing Obstacles (Figure 5.5a) 21
22
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 22
23
k. Lateral Offset of Barrier L2L2 Figure 5-39. Approach Barrier Layout Variables L2L2 23
24
Level 2 Example- Location 9 L A = 23.9’ + 1.5’ = 25.4’ Lateral Offset of Barrier L 2 = L 2 = 1’ + 11’ + 1’ = 13.0’ 24
25
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 25
26
Level 2 Example- Location 9 L A = 25.4’ L 2 = 13.0’ Y= Y = L 2 + 0.75’ Y = 13.0’ + 0.75’ Y = 13.75’ 26
27
l. Upstream End of Guardrail L2L2 Figure 5-39. Approach Barrier Layout Variables X= (L A – Y) / (L A / L R ) LALA LRLR L A - Y X 27
28
Level 2 Example- Location 9 L A = 25.4’ L 2 = 13.0’ Y = 13.75’ L R = 360.0’ Length of Need – Formula Solve for X X = (L A – Y) / (L A / L R ) X = (25.4’ – 13.75’) / (25.4’ / 360.0’) X = 165.12’ 28
29
Level 2 Example- Location 9 Obstacle SF Southface_Foundation_Station = SF SF = (3945+98.50) L AOC = Length of AOC = 3.0’ 29
30
l. Upstream End of Guardrail L2L2 Figure 5-39. Approach Barrier Layout Variables Point of Need 30
31
Level 2 Example- Location 9 Point of Need PON = SF – X PON = (3945+98.50) – 165.12’ PON = (3944+33.38) Length of Need = LON = X + L AOC LON = 165.12’ + 3.0’ LON = 168.12’ 31
32
Level 2 Example- Location 9 Distance from back of guardrail to foundation= 25.4’(L A )-3.0’(Fnd.)-13.0’(L 2 )-1.76’(Depth of GR)= 7.64’ Therefore, LON ends at downstream end of obstacle. Condition 2, TBG Figure 5.12 32
33
Level 2 Example- Location 9 Terminals Terminal = Type T2 T2 = 12.5’ (does not count toward length of need) Terminal = Type T1 (Special) T1 = 50.0’ (37.5’ counts toward length of need) Barrier Limits Determination Length of Guardrail L Guardrail = LON – T1 L Guardrail = 168.12’ – 37.5’ L Guardrail = 130.62’ L Guardrail, R = L Guardrail (Round up to the nearest 12.5’ increment) L Guardrail, R = 137.5’ 33
34
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runoutm. Upstream End of Barrier Wall e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 34
35
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runoutm. Upstream End of Barrier Wall e. Shy Line Offsetn. Downstream Terminal f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 35
36
Level 2 Example- Location 9 T2 End_Station = SF + L AOC + T2 T2 End_Station = (3945+98.50) + 3’ + 12.5’ T2 End_Station = (3946+14.00) GR End_Station = Begin T2 Station = End T2 Station – 12.5’ GR End_Station = (3946+14.00) – 12.5’ GR End_Station = (3946+01.50) GR Begin_Station = GR End_Station – L Guardrail,R GR Begin_Station = (3946+01.50) – 137.5’ GR Begin_Station = (3944+64.00) T1 Begin_Station = GR Begin_Station – 50’ T1 Station = (3944+64.00) – 50’ T1 Begin_Station = (3944+14.00) 36
37
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runoutm. Upstream End of Barrier Wall e. Shy Line Offsetn. Downstream Terminal f. Foreslope / Backslopeo. Barrier Obstacle g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 37
38
Barrier Limits Check 12.5’ < |PON- T1 Begin_Station |< 25’ 12.5’ < |(3944+33.38) – (3944+14.00)|< 25’ 12.5’ < 19.38’ < 25’ 38
39
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runoutm. Upstream End of Barrier Wall e. Shy Line Offsetn. Downstream Terminal f. Foreslope / Backslopeo. Barrier Obstacle g. Clear Zonep. Compare existing length to proposed h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 39
40
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runoutm. Upstream End of Barrier Wall e. Shy Line Offsetn. Downstream Terminal f. Foreslope / Backslopeo. Barrier Obstacle g. Clear Zonep. Compare existing length to proposed h. Clear Zone Adjustmentq. Prepare warrant text and exhibits i. Lateral Extent of the Area of Concern 40
41
Level 2 Example – Location 9 – Site Plan 41
42
Questions? 42
43
Level 2 Example- Location 17 43
44
Level 2 Example- Location 17 44 Notes: 1.There is a crash wall in front of the bridge piers. 2.Regrading of the bridge cone is not a feasible alternative.
45
Each AOC shall be analyzed separately. a. Establish EOTW 45
46
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed 46
47
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT 47
48
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout 48
49
d. Length of Runout L2L2 Figure 5-39. Approach Barrier Layout Variables LRLR 49
50
d. Length of Runout 50
51
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset 51
52
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope 52
53
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone 53
54
g. Clear Zone Select highest value in range Table 3-1 Clear Zone Distances in Feet from EOTW 54
55
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment 55
56
h. Clear Zone Adjustment 56
57
Level 2 Example- Location 17 Adjusted Clear Zone = 32’ x 1.2 = 38.4’ 57
58
Each AOC shall be analyzed separately. a. Establish EOTW b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 58
59
i. Lateral Extent of the Area of Concern L2L2 Figure 5-39. Approach Barrier Layout Variables LALA 59
60
Level 2 Example- Location 17 Lateral Extent of the Area of Concern L A = L A = 32’ x 1.2 L A = 38.4’ 60
61
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speed c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 61
62
Flowchart for Analysis of Existing Obstacles (Figure 5.5a) 62
63
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADT d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 63
64
k. Lateral Offset of Barrier L2L2 Figure 5-39. Approach Barrier Layout Variables L2L2 64
65
Level 2 Example- Location 17 L A = 38.4’ L 2 = L 2 = 12.0’ (11’ + 1’) 65
66
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runout e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 66
67
Level 2 Example- Location 17 L A = 38.4’ Lateral Offset of Barrier L 2 = 12.0’ (11’ + 1’) Y = Y = L 2 + 0.75’ Y = 12.0’ + 0.75’ Y = 12.75’ 67
68
l. Upstream End of Guardrail < L R LALA L2L2 Y X Figure 5-48. Example of Barrier Design for Fixed Object on Horizontal Curve Graphical Determination of “X” 68
69
Level 2 Example- Location 17 L A = 38.4’ L 2 = 12.0’ (11’ + 1’) Y= Y = L 2 + 0.75’ Y = 12.0’ + 0.75’ = 12.75’ Obstacles BP Bridge_Pier_Station = BPBP = (132+35.72) EC Embankment_Cone_Station = ECEC = (132+18.58) L AOC = BP-EC L AOC = 17.14’ (assumes that EC ends at BP) Length of Need – Graphical Solution Tangent Runout Path from EC = 474.85’ Tangent Runout Path = 474.85 > L R = 300.0’ Therefore, use L R to determine upstream end of the runout path X = Calculated Graphically = 166.65’ 69
70
Level 2 Example- Location 17 Point of Need = PON PON = EC – X PON = (132+18.58) – 166.65’ PON = (130+51.93) Length of Need = LON LON = X + L AOC LON = 166.65’ + 17.14’ LON = 183.79’ 70
71
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runoutm. Upstream End of Barrier Wall e. Shy Line Offset f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 71
72
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runoutm. Upstream End of Barrier Wall e. Shy Line Offsetn. Downstream Terminal f. Foreslope / Backslope g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 72
73
Level 2 Example- Location 17 Terminals Terminal = Type T6B T6B = 43.15’ (counts toward length of need) Terminal = Type T1 (Special) = T1 = 50.0’ (37.5’ counts toward length of need) Barrier Limits Determination Length of Guardrail L Guardrail = LON – T6B – T1 L Guardrail = 183.79’ – 43.15’ – 37.5’ L Guardrail = 103.14’ L Guardrail, R = L Guardrail (Round up to the neareast 12.5’ increment) L Guardrail, R = 112.5’ 73
74
Level 2 Example- Location 17 T6B End_Station = BP T6B End_Station = (132+35.72) GR End_Station = End T6B Station – 43.15’ GR End_Station = (132+35.72) – 43.15’ GR End_Station = (131+92.57) GR Begin_Station = GR End_Station – L Guardrail,R GR Begin_Station = (131+92.57) – 112.5’ GR Begin_Station = (130+80.07) T1 Begin_Station = GR Begin_Station – 50’ T1 Begin_Station = (130+80.07) – 50’ T1 Begin_Station = (130+30.07) 74
75
Barrier Limits Check: 12.5’ < |PON – T1 Begin_Station |< 25’ 12.5’ < |(130+51.93) – (130+30.07)| < 25’ 12.5’ < 21.86’ < 25’ 75
76
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runoutm. Upstream End of Barrier Wall e. Shy Line Offsetn. Downstream Terminal f. Foreslope / Backslopeo. Barrier Obstacle g. Clear Zone h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 76
77
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runoutm. Upstream End of Barrier Wall e. Shy Line Offsetn. Downstream Terminal f. Foreslope / Backslopeo. Barrier Obstacle g. Clear Zonep. Compare existing length to proposed h. Clear Zone Adjustment i. Lateral Extent of the Area of Concern 77
78
Each AOC shall be analyzed separately. a. Establish EOTWj. Warrant Analysis Level b. Design Speedk. Lateral Offset of Barrier c. Design ADTl. Upstream End of Guardrail d. Length of Runoutm. Upstream End of Barrier Wall e. Shy Line Offsetn. Downstream Terminal f. Foreslope / Backslopeo. Barrier Obstacle g. Clear Zonep. Compare existing length to proposed h. Clear Zone Adjustmentq. Prepare warrant text and exhibits i. Lateral Extent of the Area of Concern 78
79
Level 2 Example- Location 17 – Site Plan 79
80
Questions? 80
81
Example-Speed Profile 81
82
Site Plan 82
83
Acceleration Table Table 10-3 Minimum Acceleration Lengths for Entrance Terminals with Flat Grades of Two Percent or Less 83
84
Example-Speed Profile-Site Plan 30 MPH 40 MPH 50 MPH 60 MPH 70 MPH 84
85
Level 3 Example – Overhead Sign Truss 85
86
Level 3 Example – Plan 86
87
Flowchart for Analysis of Proposed Obstacles (Figure 5.5b) 87
88
New Overhead Sign Truss (Span and Cantilever) Article 5.5.9 The Designer shall perform a Level 3 Analysis to determine the most cost-effective design for all new overhead sign installations. The alternatives at minimum to evaluate shall include: (1) base condition – shortest span or arm with shielding; (2) span or arm length which places foundation outside defined clear zone with no shielding or if clear zone is undefined places foundation such that the criteria in Table 5.6.1 is met; (3) longer span or arm which places foundation well outside the clear zone with no shielding. 88
89
Level 3 Example – Overhead Sign Truss Analyze 4 Alternatives for Sign Foundation (Assumes Clear Zone is defined) 1.Base Condition: Foundation Shielded by Guardrail 2.Foundation Beyond Clear Zone, not shielded 3.Foundation on Backslope, not shielded 4.Foundation on Backslope, not shielded (max. length truss) 89
90
Level 3 Example – Plan 90
91
Level 3 Example – Cross Section 91
92
Level 3 Example – Cross Section 92
93
Level 3 Example – Cross Section 93
94
Level 3 Example – Cross Section 94
95
Sign Structure Foundation 95
96
Level 3 Example – Feature Sketch 96
97
Level 3 Example – Guardrail Calculation 97
98
Level 3 Example – Guardrail Calculation 98
99
Level 3 Example – Guardrail Calculation 99
100
Level 3 Example – Estimated Costs 100
101
Cost Tab 101
102
Highway Tab 102
103
Segments Tab 103
104
Features Tab 104
105
View Pulldown 105
106
View/ Crash Cost 106
107
View/ Crash Cost/ KABCO 107
108
Options/ Units 108
109
Option/ Edit Feature 109
110
Option/ Edit Feature 110
111
Edit Feature 111
112
Features/ Category 112
113
Features / Category/ User Defined 113
114
Feature/ Types 114
115
RSAP Output 115
116
RSAP Output 116
117
RSAP Output 117
118
RSAP Output 118
119
RSAP Output 119
120
RSAP Output 2 vs. 3 3 vs. 4 4 vs. 1 120 3 is better 4 is better
121
AOC’s in Close Proximity
122
14+25 Culvert - AOC #1 14+00 17+22 Cantilever Sign- AOC #2 15+70 16+12.5 17+05 Upstream Terminal End 18+30 18+42.5 Downstream Terminal End Upstream Terminal End Downstream Terminal End 92.5’ Gap Total Length of Need = 405’ EOTW AOC’s in Close Proximity 122 PON 16+00 18+27 14+05
123
Example- AOC Table Format AOC#UPSTREAM US TERM PONDS End of Guardrail DOWNSTREAM DS TERM GAP (FT) OVERLAP (FT) 114+0014+2516+0016+12.50 92.50--- 217+0517+2218+3018+42.50 123
124
Summary Calculation LON = AOC #2 DS End of GR – AOC #1 PON = (18+30)-(14+25) = 405’ Terminals DS Terminal= TBT Type T2=T2 US Terminal= TBT Type T1=T1 124
125
Barrier Limits Determination L Guardrail = LON-T1 = 405’-37.5’ = 367.5’ L G, rounded = 367.5/12.5’ = 29.4, round to 30 sections 30 x 12.5’ = 375’ T2 end = DS End of GR+ 12.5’=18.30 + 12.5’= 18+42.5 Gr end = AOC #2 DS End of GR = 18+30 Gr begin = Gr end - L G, rounded = 18+30 - 375’ = 14+55 T1 end = Gr begin = 14+55 T1 begin = T1 end - 50’ = 14+55-50’ = 14+05 125
126
Barrier Limits Check 12.5’ < AOC #1 PON – T1 begin < 25’ AOC #1 PON – T1 begin 14+25-14.05= 20’ Provide a Summary Site Plan 126
127
14+25 Culvert - AOC #1 14+00 17+72 Cantilever Sign- AOC #2 15+70 16+12.5 17+55 Upstream Terminal End 18+80 18+92.5 Downstream Terminal End Upstream Terminal End Downstream Terminal End 142.5’ Gap EOTW AOC’s in Close Proximity 127 PON 16+00 18+77 Length of Need Length of Need
128
14+25 Culvert - AOC #1 14+12.5 16+22 Cantilever Sign- AOC #2 15+70 16+12.5 16+05 Upstream Terminal End 17+30 17+42.5 Downstream Terminal End Upstream Terminal End Downstream Terminal End 7.5’ Overlap Total Length of Need EOTW AOC’s in Close Proximity 128 PON 16+00 17+27 14+17.5
129
Example- AOC Summary Table Format LEGEND POINT OF NEED STATION DOWNSTREAM END OF GUARDRAIL STATION AOC SUMMARY TABLE AOC 115+0026+00 AOC 215+0022+50 AOC 316+2527+00 AOC 4 19+00 23+00 SUMMARY15+0027+00 TOTAL LON15+00 to 27+00 = 1,200 FT
130
AOC- Color Coded System
131
Questions? 131