Project Management – Part 1
2
Overview What is a project? Project management techniques Activity lists Network diagrams Critical path analysis Gant charts
3
Definition Project a series of jobs usually directed toward some major output and requiring a significant period of time to perform Over the next few days we’ll cover some project management techniques…
4
Activity Lists Breakdown of all activities/tasks in a project Precedence constraints One task can’t be started until another is finished Duration of activities
5
Activity List for Example Problem Activity Description Immediate Predecessors Required Activity Time (weeks) A B C D E F G H I J Select office site Create organization and financial plan Determine personnel requirements Design facility Construct the interior Select personnel to move Hire new employees Move records, key personnel, etc. Make financial arrangements Train new personnel - - B A,C D C F F B H,E,G 3 5 3 4 8 2 4 2 5 3
6
Network Diagrams Show the sequence of activities in a project Consists of nodes and arrows Nodes show activities (AON: activity on node) Arrows show precedence We won’t cover AOA (activity-on-arrow) So don’t worry about p. 270-271
7
A
8
A B
9
A BC
10
A BC
11
A BC
12
A B D C
13
A B D C
14
A B D C
15
A B D C E
16
A B D C E F
17
A B D C E F G
18
A B D C E F G H
19
A B D C E F G H I
20
A B D C E F G H I J 5 3 3 4 2 8 4 2 3 5
21
Critical Path Analysis Find all paths and compute expected length ADEJ BCDEJ BCFGJ BCFHJ BI Longest path is duration of the project Delays in activities on the critical path will delay the project = 18 = 23 = 17 = 15 = 10 Critical Path
22
Early Start/Early Finish (ES/EF) The earliest an activity can be started and finished (without delaying the project). ES = 0 if no predecessors ES = maximum EF of the predecessors EF = ES + activity duration Work forward through time
23
A B D C E F G H I J 0 5 3 3 4 2 8 4 2 3 5 ES = 0 because no predecessors EF = 3 since 0 + 3 = 3 ESEF
24
A B D C E F G H I J 0 3 5 5 3 3 4 2 8 4 2 3 5 ESEF 0
25
A B D C E F G H I J 0 3 0 5 5 5 3 3 4 2 8 4 2 3 5 ESEF
26
A B D C E F G H I J 0 3 0 55 8 5 3 3 4 2 8 4 2 3 5 ESEF
27
A B D C E F G H I J 0 3 0 55 8 5 5 3 3 4 2 8 4 2 3 5 ESEF
28
A B D C E F G H I J 0 3 0 5 5 8 5 10 5 3 3 4 2 8 4 2 3 5 Remember: ES is always the largest of the predecessors’ Early Finishes ESEF
29
A B D C E F G H I J 0 3 0 5 5 8 5 10 8 5 3 3 4 2 8 4 2 3 5 ESEF
30
A B D C E F G H I J 0 3 0 55 8 5 10 8 12 5 3 3 4 2 8 4 2 3 5 ESEF
31
A B D C E F G H I J 0 3 0 5 5 8 5 10 8 12 8 12 5 3 3 4 2 8 4 2 3 5 ESEF
32
A B D C E F G H I J 0 3 0 55 8 5 10 8 12 8 10 12 20 5 3 3 4 2 8 4 2 3 5 ESEF
33
A B D C E F G H I J 0 3 0 55 8 5 10 8 12 8 10 12 20 10 5 3 3 4 2 8 4 2 3 5 ESEF
34
A B D C E F G H I J 0 3 0 5 5 8 5 10 8 12 8 10 12 20 10 12 10 14 5 3 3 4 2 8 4 2 3 5 ESEF
35
A B D C E F G H I J 0 3 0 5 5 8 5 10 8 12 8 10 12 20 10 12 10 14 20 5 3 3 4 2 8 4 2 3 5 ESEF
36
A B D C E F G H I J 0 3 0 5 5 8 5 10 8 12 8 10 12 20 10 12 10 14 20 23 5 3 3 4 2 8 4 2 3 5 ESEF
37
Late Start/Late Finish (LS/LF) The latest an activity can start and finish (without delaying the project) If last activity, LF = EF of last activity on critical path LF = minimum LS of successors LS = LF – activity duration Work backwards through time
38
A B D C E F G H I J 23 5 3 3 4 2 8 4 2 3 5 Remember: at the last activity, LF = EF of last activity on Critical Path LF 20 23 ESEF
39
A B D C E F G H I J 20 23 5 3 3 4 2 8 4 2 3 5 LFLS
40
A B D C E F G H I J 20 23 23 5 3 3 4 2 8 4 2 3 5 LFLS
41
A B D C E F G H I J 20 23 18 23 5 3 3 4 2 8 4 2 3 5 LFLS
42
A B D C E F G H I J 20 23 18 23 20 5 3 3 4 2 8 4 2 3 5 LFLS
43
A B D C E F G H I J 20 23 18 23 20 12 20 5 3 3 4 2 8 4 2 3 5 Recall, LF is equal to the smallest LS of the activity’s successors LFLS 16 18
44
A B D C E F G H I J 20 23 18 23 18 20 16 20 12 20 16 5 3 3 4 2 8 4 2 3 5 LFLS
45
A B D C E F G H I J 20 23 18 23 18 20 16 20 12 20 14 16 5 3 3 4 2 8 4 2 3 5 LFLS
46
A B D C E F G H I J 20 23 18 23 18 20 16 20 12 20 12 14 16 5 3 3 4 2 8 4 2 3 5 LFLS
47
A B D C E F G H I J 20 23 18 23 18 20 16 20 12 20 8 12 14 16 5 3 3 4 2 8 4 2 3 5 LFLS
48
A B D C E F G H I J 20 23 18 23 18 20 16 20 12 20 8 14 16 8 12 5 3 3 4 2 8 4 2 3 5 LFLS
49
A B D C E F G H I J 20 23 18 23 18 20 16 20 12 20 5 8 14 16 8 12 5 3 3 4 2 8 4 2 3 5 LFLS
50
A B D C E F G H I J 20 23 18 23 18 20 16 20 12 20 5 8 14 16 8 12 8 5 3 3 4 2 8 4 2 3 5 LFLS
51
A B D C E F G H I J 20 23 18 23 18 20 16 20 12 20 5 8 14 16 8 12 5 8 5 3 3 4 2 8 4 2 3 5 LFLS
52
A B D C E F G H I J 20 23 18 23 18 20 16 20 12 20 5 8 14 16 8 12 5 8 5 5 3 3 4 2 8 4 2 3 5 LFLS
53
A B D C E F G H I J 20 23 18 23 18 20 16 20 12 20 5 8 14 16 8 12 5 8 0 5 5 3 3 4 2 8 4 2 3 5 LFLS
54
A B D C E F G H I J 0 3 0 55 8 5 10 8 12 8 10 12 20 10 12 10 14 20 23 18 23 18 20 16 20 12 20 5 8 14 16 8 12 5 8 0 5 5 3 3 4 2 8 4 2 3 5 LFLS ESEF
55
Slack The most you can delay an activity without delaying the project Slack = LS - ES = LF - EF Critical activities have zero slack Helps to set priorities, scrutiny of management
56
A B D C E F G H I J 0 3 0 55 8 5 10 8 12 8 10 12 20 10 12 10 14 20 23 18 23 18 20 16 20 12 20 5 8 14 16 8 12 5 8 0 5 5 3 3 4 2 8 4 2 3 5 LFLS ESEF Critical activities have zero slack
57
A B D C E F G H I J 0 3 0 55 8 5 10 8 12 8 10 12 20 10 12 10 14 20 23 18 23 18 20 16 20 12 20 5 8 14 16 8 12 5 8 0 5 5 3 3 4 2 8 4 2 3 5 LFLS ESEF Critical activities have zero slack
58
Gantt Chart: Early Start/Finish 123456789 1011121314151617181920212223 A B C D E F G H I J Early Start of Activity F Late Finish of Activity F Scheduled Time of Activity F 0
59
Gantt Chart: Late Start/Finish 123 4 56789 1011121314151617181920212223 A B C D E F G H I J
61
For next time Finish reading the project management chapter