L4 BCC – 1 Sep 2011 F. Roncarolo, U. Raich L.Soby, J.Tan, C.Zamantzas, F. Lenardon, C.Vuitton, G-J.Focker
2
DESIGN Completed for almost all instruments (most of TL devices == L4 monitors) Basically all devices will be tested at 3 MeV test stand Open issues –Number of devices and locations: need frozen layout Once done: details about interconnections –Profile monitor in dump line (see later slide) –BLM detector type (see later slide) –Equipment of TL with station for laser stripping R&D SCHEDULE / BUDGET Present advancement/plans/budget for design, fabrication, cabling and installation under control BI Linac 4 review (with reviewers panel) on October 18 th (tbc and announced in the next few days) F. Roncarolo, U. RaichL4 BCC - 01 Sep 20112
3
3F. Roncarolo, U. Raich 3 BTVs now replaced by 1 WS or SEM GRID (H+V) From Layout DB 31-08-11
4
L4 BCC - 01 Sep 20114F. Roncarolo, U. Raich Copy of LEBT monitors –100 mm diameter –Up to 200 MHz sampling rate Acquisition sync. with the distributor, to know how much beam current goes to each PSB ring –Electronics ready for such option –Need FPGA code update (likely not possible before LS1) In general –Do we agree on the number of devices? –Foreseen by BI : 6, Layout DB: 7
5
Shorted strip-line detectors –Same design for all L4 BPMs –Diameter for TL monitors: 100 mm, L = ~250mm –Electronics with down-mixing of 22 MHz maximum sampling rate 4x22=88 MHz –50 ns pulse length beam position measurement foreseen by the design (noise levels to be investigated) For TL: is # of monitors and location frozen ? At the moment of installing TL BPMs: will it be possible to change the 17 old TL monitors (after BHZ20)? F. Roncarolo, U. RaichL4 BCC - 01 Sep 20115 J. Tan
6
Same design as all L4 monitors – will require reduced pulse length (100us) Mechanics ~ on schedule, 140 mm flange-to-flange (PIMs type) New electronics under development, to be tested on 3 MeV test stand –200 kHz ADC band (5 us) –Wire polarization –New connectors and cables: 32 channels in 1 cable F. Roncarolo, U. RaichL4 BCC - 01 Sep 20116 Is this up to date? Once frozen: verify details of flange connections
7
3 screens option abandoned Additional monitor not included in BI plans –What are requirements? –SEM Grid or WS ? Spare L4 SEM grid –single shot meas –24 wires fixed pitch Spare L4 WS –multishot meas –40 um resolution (wire diam.) SEM grid on stepping motor –Not foreseen by BI (can recuperate test bench device?) –Not single shot but can improve resolution with less shots than WS new SEM with variable resolution (by variable rotation w.r.t. beam axis) –not foreseen design new or try to recuperate L2 type device –When rotation != 90 deg: during single shot the sampling is done at different longitudinal locations F. Roncarolo, U. RaichL4 BCC - 01 Sep 20117
8
F. Roncarolo, U. RaichL4 BCC - 01 Sep 20118 W.Vigano, C. Zamantzas Auto-gain switching -Integrated detector signal sampled every 2 us -From pA to mA detector output current 2 us : sampling the integral Electronics under development, in parallel to L4 linac and PSB new electronics Special screened cables to minimize EM noise (problem in other world-wide linacs) TL cable installation on stand-by while waiting for latest beam optics and BLM location s Every second BLM location is equipped with a spare cable to host an additional monitor if needed Choice of detector (Ionization chamber, chamber type, or possibly other detectors) under discussion Wide dynamic range expected !
9
Aim at profile + emittance measurement For testing @ Linac 4 –At least 1 station –Y chamber @ dipole –Establish laser location and optical line path If there will be no intermediate dump between 1st bend and BI line: –can test only laser stripping and profile meas (no emitt. meas) with a station after PIMS F. Roncarolo, U. RaichL4 BCC - 01 Sep 20119 LASER stripping H0 monitor Possible locations
10
BCT – BPM –Low level completed or well on the way to completion –Need OP GUI development –All will be tested at 3 MeV test stand SEM grids –Low level and OP GUI done, being used at test stand BLM –Definition of the memory map CPU in readout simulation mode Start development of driver, RT software, etc. –First version of memory map (LINAC4) - end of September F. Roncarolo, U. RaichL4 BCC - 01 Sep 201110
11
F. Roncarolo, U. RaichL4 BCC - 01 Sep 201111
12
F. Roncarolo, U. RaichL4 BCC - 01 Sep 201112
13
F. Roncarolo, U. RaichL4 BCC - 01 Sep 201113