Status of Contributions, Draft Budget Request for 2005 and Outlook for the Longer Term Future Martyn Davenport 8 TH October 2004 CAST FRC-D 2003-11
2
Status of Common Fund (T297400) General level of contributions from all institutes Cash contributions 886.6 kCHF (Table 1) Expenditure inside institutes 1057.6 kCHF(Table 2) Time profile of contributions and expenditures (Table 3 & 4 respectively) Sum over all years now amounts to 1.942 M CHF > 98% promised in MOU Some institutes have exceeded their committements Others still have outstanding committements ( 4.4 % of original MOU) Common Fund balance on 15.09.04 43.6k CHF (Table 3)
3
Table 1: Details of CF Cash contributions (up to 17.09.04) Table 2 : Details of expenditure in collaborating institutes (excl. CERN) (up to 17.09.04) Table 3: Common Fund Budget T297400 (up to 17.09.04) Table 4: Expenditure of collaborating institutes (up to 17.09.04)
4
Outstanding Committements Outstanding contributions from the CAST Institutes: 136 kCHF (4.4%) These contributions are crucial to the successful and timely transition to Phase II in the first half of 2005. (see Section 3) CERN contribution to magnet operation (1265 kCHF): Summary of magnet operation costs (see table 8) 995 kCHF used by end of 2004 Remainder can be used for the shorter program in 2005
5
Table 6 : Total financial Contributions as agreed in MOU - updated
6
Table 7 : Status of Common Fund Contributions (excl. CERN magnet operation)
7
Table 8 : Status of Common Fund Contributions (incl. CERN magnet operation)
8
Draft Budget Request 2005 2005 is a transition year for CAST Program for 2005 (next slide) Draft operating budget must take into account Maintenance of experiment (phones,rentals,infrastructure) Extensions to Slow Control for Vacuum and 4 He system Seed money for Cold Window R&D and ordering of final windows Fees for external survey team Mechanical support: designer and mechanic for small modifications in SR8 Subsistence/support for key personnel, including new doctoral student working on final 3 He gas system for 2006 Estimate is 156 kCHF
9
2005 program Modifications to magnet movement system and ‘Potence’ Detailed checking of magnet tracking behaviour Installation of a new vacuum system Preparation of a provisional 4 He gas system Opening of the magnet cryostat Install cold windows and additional instrumentation Cool down and 4 He test filling of magnet cold bore Quench tests Commission gas system First low-pressure 4 He data taking runs (Second half 2005 – final design and ordering of Phase II gas system)
10
Table 5: Draft operating budget 2004
11
2005 is a transition year for CAST Program for 2005 (next slide) Draft operating budget must take into account Maintenance of experiment (phones,rentals,infrastructure) Extensions to Slow Control for Vacuum and 4 He system Seed money for Cold Window R&D and ordering of final windows Fees for external survey team Mechanical support: designer and mechanic for small modifications in SR8 Subsistence/support for key personnel, including new doctoral student working on final 3 He gas system for 2006 Draft Budget Request 2005
14
2005 items not covered by request New vacuum system and provisional 4 He gas system Funds have been earmarked by Freiburg for this (90kCHF) Mechanical modifications to magnet and Potence New request to PH for 100kCHF as contribution to Phase II MOU Costs of final gas system and upgrades to CAST Subject to a new MOU for the second phase MOU under preparation (see later)
15
Overall financial situation and future outlook Operating budget 2005 2005 budget should normally be covered by a new MOU for second phase. New MOU: Operating Budget ~ 3.5kCHF/person post doc or above in CAST 6 months delay New funding will not available before 2H2005 Outstanding contributions to existing MOU crucial to operations in 1H2005 Summary of situation
16
Summary of overall financial situation Some funds available for 2005 But not enough to bridge to the new MOU We miss the contributions from Greece (40k) and USC (7k) We have adequate funds for vacuum and 4 He gas system Potential problem with timing of project money from PH Magnet movement system - modifications may be delayed CAST memo to D Schlatter PH under preparation 38% of requirements
17
Future outlook New MOU (K Zioutas) 2005-2007 Present estimates 2005-2007 COLLABORATION 1215 kCHF –Phase II systems & manpower740 –General CAST hardware upgrades100 –Operating budget 375 CERN 1250 kCHF –Project money (mechanical modifications)100 –Exploitation350 –Magnet operation800 Villars ’04 – catalyst for longer term plans H 2 running 2008-2010 (cold gas cell in at least 1 beam pipe) Double axion mass reach (0.8 1.5 eV/c 2 ) Development of gas cell(s) and Si detectors for cell windows (30ºK)
18
CAST – gas cell option 2006 PHASE II with 4 He 5K (0-166 mbar) Inside gas cell fitted with thin cold windows and external x-ray detectors (or solid Si-detector windows?) 2006 PHASE II data taking with 3 He 1.8K higher pressure ( 0- 60 mbar) Thin cold windows external x-ray detectors Start 2005 Design study for Phase II Gas system (2 options) Late 2005 PHASE II data taking with low pressure 4 He 1.8K (0-6 mbar) PHASE 1 ( vacuum ) Mid 2005 Install cold windows and simple gas system 2H2005 PHASE II Low pressure 4 He 1.8K tests with cold windows Start 2005 Modifications to magnet movement system and cable support arm 2008 onwards (?) PHASE III data taking with H 2 30K (0- 4 bar) inside gas cell fitted With solid Si-detector windows Mid 2005 Decision on option 2H2005 Ordering and construction