1
November 2015
2
4 E – Toilets 8 e-toilets operational and 4 more e- toilets work in progress. Under Ground Drainage System Completed & Tender Published Estate survey Contract Awarded & work in progress Improvement of road geometry at WIPRO junction Construction of compound wall in progress.
3
3 Permanent Works - Under Progres WIPRO Neeladri RoadTessolve/ Edizi Tools Road
4
4 Permanent Works - Under Progres Quasitum RoadE-city Survey
5
5 Permanent Works - Under Progres C-Dot D-Mart RoadAlong KFC/Svenska
6
6 Permanent Works - Completed IIITB EntranceKSSIDC Complex
7
7 Road Maintenance Work - Under Progres HP Avenue Road Widening Completed HP Avenue Road Wet Mix Work under progress
8
8 Maintenance – Under Progress
9
9 20 feet deep well Rainwater Harvesting Pit at Various locations Maintenance works – Completed
10
10 Construction of 300KLD Conventional STP in ELCIA Park. Total Project Cost - Rs. 75,72,798/- (Including Civil & STP works) Permanent Works – Under Progress
11
11 Road Maintenance Work - Completed Pot holes in front of TCS, Phase 2 Pot holes in front of Infosys Edge verve, Phase 1
12
12 Road Maintenance Work - Completed Pot holes @ NTTF Boys hostel turning, Phase 1 Pot holes @ WIPRO Gate 5, Phase 1
13
13 Tender Published Finalising Technology, Design, Establishment and Commissioning of 400 KLD Sewage Treatment Plant at Electronics City, Including Operation and Maintenance of the Treatment Plant for a Period of ONE (1) year. Finalising Technology, Design, Establishment and Commissioning of 1 MLD Capacity Sewage Treatment Plant at Electronics City, Including Operation and Maintenance of the Treatment Plant for a Period of ONE (1) year.
14
14 Contracts Awarded Providing UGD System to connect 300KLD STP, Electronics City Phase 1, Bangalore - 560 100. – Under Evaluation Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs Bhavani Industries Road Providing and laying of Asphalting using 60/70 grade bitumen from C-DOT to D-Mart Road Junction Wipro Avenue 4th cross to Wipro Avenue 5th cross road via Y-junction Wipro gate 5 to Wipro gate 6 Haritha IT/Fire Station Road
15
15 Contracts on Anvil Providing and laying of Asphalting using 60/70 grade bitumen from Fire station to Canara bank road Junction Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along TCS Road Fire Station to Canara Bank Junction Radel Industries Road
16