Download presentation
Presentation is loading. Please wait.
Published byAubrey Shepherd Modified over 8 years ago
1
1 Large infrastructure projects − dealing with the public sector ESCL Conference, August 25, 2006 Stuart Graham President and CEO, Skanska AB
2
2 Large infrastructure projects are LARGER! From billions of SEK to billions of Euros More complex − public exposure, technical risks Long duration − 4, 5, 6 years
3
3 Increased construction risks Size of project = size of financial exposure Interface with public Tendered project and built project – not the same
4
4 Shifting of uncontrollable risks to contractor Unreasonable − non/technical risks to contractor
5
5 Example In the event of a delay caused by the owner the contractor’s sole remedy will be on extension of time. NO MONEY.
6
6 Example The contractor shall, without any right to compensation for costs or extension of time, perform such works that are a consequence of unexpected or changed conditions at the site.
7
7 Example Any claim for a changed condition or an extension of time must be submitted to the owner in 48 hours of the onset of the event causing such claim.
8
8 Example The contractor shall be liable for direct and indirect damages the owner may suffer as a result of delay in completion of the project.
9
9 Why the shift of unreasonable risks Lack of adequate budget and contingency Lack of qualified resources Contractors have taken risks for free
10
10 Another prevelant tactic Ignore changed condition clauses No resolution Post construction legal procedures Cost taken by ”next guy”
11
11 Example of all issues − Södra Länken Large complex projects Long duration Contractors accepted additional risk for free Settlements long after completion
12
12 Response to current conditions in public infrastructure market Disciplined risk assessment, legal and technical Mitigation of quantifiable risks with money (even low profitability risks) Add resources to cost of tenders Raise the price (risk&reward) Refuse unacceptabel risk
13
13 During construction − how to act Deliver! Committ necessary resources Follow the contract to the letter Expect the worst − not ”partnering” Ethical and Civility
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.