ESS CRYOMODULE RISKS REGISTER ESS CRYOMODULE COMPONENTS AND CAVITY EXPERTISE Franck PEAUGER14th January 2016
2
RISK REGISTER ESS CRYOMODULE COMPONENTS | PAGE 2
3
CAVITY EXPERTISE | PAGE 3 Transfert : ESS schedule will explicit limit of responsibilities and change instruction provisions (studies) Mitigation : involvement in Configuration Control Board + close follow-up of accounted hours CEA responsability is directly or undirectly engaged + demands from ESS partners exceed the allocated budget -> CEA support the impact (performance, cost)
4
COUPLERS | PAGE 4 No industrial company is qualified before the contract + Couplers prototype is qualified by separate parts then integrated and tested by CEA -> Pre-serie will not reach the expected performance during conditionning Analyze schedule impacts with different procurement scenario. Possible multisourcing (2 minimum). Keep the companies involved in prototypes in the business
5
RF TEST STAND FOR POWER COUPLER CONDITIONNING | PAGE 5 Commissioning of RF source may last 12 months to achieve full reliability (3 months commissioning planned) -> RF source lack of reliability at he start Prioritirize the RF source procurement + Prepare the installation in advance Couplers
6
COUPLER DOORKNOB | PAGE 6 Couplers doorknob definition is new and technically challenging: -> Couplers doorknob do not respect specifications or difficult to manufacture Test in Spring 2016 : no mitigation except what is foreseen (risk should be re- evaluated) RF trap Kapton insulation
7
CRYOSTAT COMPONENTS (GASKETS) | PAGE 7 CRYOSTAT COMPONENTS Aluminium material difficult to procure: -> Un-availability of Aluminium gaskets for assembly Procurement of material in advance and test other material
8
CRYOSTAT COMPONENTS (TUNER MOTORS) | PAGE 8 Tuner motor: only one provider (TSA) -> Un-availability of tuner motors for assembly Procure all the items (128) asap + proper storage conditions (packaging)
9
RISK REGISTER ESS CRYOMODULE COMPONENTS | PAGE 9 Before mitigationAfter mitigation Synthesis - Risk portfolio Criticity matrix +1 retention
10
Commissariat à l’énergie atomique et aux énergies alternatives Centre de Saclay | 91191 Gif-sur-Yvette Cedex T. +33 (0)1 69 08 xx xx | F. +33 (0)1 69 08 99 89 Etablissement public à caractère industriel et commercial | RCS Paris B 775 685 019 | PAGE 10 CEA Saclay/Irfu projet ESS | DATE