Option 1 New Construction (10,000 Square Feet) – Secure Entrance / Administrative Offices – Lobby / Connection to Greeno Building – Weight Room Renovations.

Similar presentations


Presentation on theme: "Option 1 New Construction (10,000 Square Feet) – Secure Entrance / Administrative Offices – Lobby / Connection to Greeno Building – Weight Room Renovations."— Presentation transcript:

1 Option 1 New Construction (10,000 Square Feet) – Secure Entrance / Administrative Offices – Lobby / Connection to Greeno Building – Weight Room Renovations – Accessible Restrooms (HS / Junior High / Elementary) – Correct Building Code Exiting Concerns at Junior High Building – Elevators at Junior High and Elementary Buildings – Renovate Existing Greeno Building Locker Rooms – Basic Mechanical / Electrical Upgrades Electrical System A/C at Junior High and High School

2 Option 1 $6,275,000

3 Option 2 New Construction (19,000 Square Feet) – Secure Entrance / Administrative Offices – Commons / Connection to Greeno Building – Kitchen / Servery – Weight Room Renovations – Accessible Restrooms (HS / Junior High / Elementary) – Elevators at Junior High and Elementary Buildings – Art / Chorus – Remodel High School Classrooms – Renovate Existing Greeno Building Locker Rooms – Extensive Mechanical / Electrical Upgrades Electrical System Data Wiring A/C at Junior High and High School Building Sprinkler at High School and Junior High

4 Option 2 $12,015,000

5 Option 2 $12,015,000

6 Option 3A New Construction (120,000 Square Feet) – Completely New K-12 School on the Existing Site Constructed in a Single Project over Multiple Phases Single Story Elementary / 2 Story Junior High & High School Maintain Greeno Building (shop and gym) Renovations – Renovate Existing Greeno Building Locker Rooms

7 Option 3A $22,935,000

8 Option 3B Completely New K-12 School on Existing Site – Constructed in Two Separate Projects New Construction (64,000 Square Feet) – Elementary Classrooms – Secure Entrance / Administrative Offices – Commons / Connection to Greeno Building – Kitchen / Servery – Auxiliary Gym – Weight Room Renovations – Accessible Restrooms (HS / Junior High) – Elevator at Junior High – Art / Chorus – Remodel High School Classrooms – Renovate Existing Greeno Building Locker Rooms – A/C at Junior High and High School Future (56,000 Square Feet) – Junior High / High School – Theater

9 Option 3B $14,850,000

10 Option 3B - Future

11 Option 4A New School on a New Site – 120,000 Square Feet – Maintain Existing Greeno Building Remodel Locker Rooms New Weight Room Option 4B New School on a New Site – 160,000 Square Feet – Replace Greeno Building $22,140,000 $29,260,000

12 Option 4C New Elementary School on a New Site (60,000 Square Feet) Existing Site New Construction (10,000 Square Feet) – Secure Entrance / Administrative Offices – Commons / Connection to Greeno Building – Weight Room Renovations – Accessible Restrooms (HS / Junior High) – Elevator at Junior High – Art / Chorus – Renovate Existing Greeno Building Locker Rooms – A/C at Junior High and High School Future (60,000 Square Feet) – Junior High / High School – Theater

13 Option 4C $16,800,000

14 Option 4C - Future


Download ppt "Option 1 New Construction (10,000 Square Feet) – Secure Entrance / Administrative Offices – Lobby / Connection to Greeno Building – Weight Room Renovations."