SAT Plans for System R&D Signal Recycling Construction and A&I Short Suspension Upgrade Roberto Passaquieti Università di Pisa and INFN-Pisa AdV Review.

Similar presentations


Presentation on theme: "SAT Plans for System R&D Signal Recycling Construction and A&I Short Suspension Upgrade Roberto Passaquieti Università di Pisa and INFN-Pisa AdV Review."— Presentation transcript:

1 SAT Plans for System R&D Signal Recycling Construction and A&I Short Suspension Upgrade Roberto Passaquieti Università di Pisa and INFN-Pisa AdV Review – Cascina, Nov. 3rd, 2008

2 AdV Review - November 3rd, 2008 2 The Virgo Superattenuator VIRGO Thermal Noise Filter Zero Standard Filters Inverted Pendulum Filter Seven Payload: Marionette Ref. Mass Mirror GROUND

3 AdV Review - November 3rd, 2008 3 SA Passive Attenuation Vertical Horizontal VIRGO Thermal Noise Measured Upper Limit

4 AdV Review - November 3rd, 2008 4 SA Passive Performance vs AdV VERTICAL HORIZONTAL 6 x 10 -18 m Hz -1/2 Upper limits of residual seismic vibrations along the beam are close to the VIRGO thermal noise Final systematic check in VIRGO +

5 AdV Review - November 3rd, 2008 5 Payload Swing Ground Seismic Noise Residual Mirror Seismic Noise Inertial Damping

6 AdV Review - November 3rd, 2008 6 Swing induced by resonances < 0.1  m Inertial Damping ADCDSPDAC Coil-Magnet actuators Acceleromters LVDT Ground Frame

7 AdV Review - November 3rd, 2008 7 Payload Swing Reduction Performance  Wide payload swing during windy days, when seismic noise below 200 mHZ is dominated by ground tilt  Too large correction dynamics for AdV requirements WIND SEA MARIONETTA CORRECTION  For principle reasons the ACC can not distinguish tilt affecting ID  A sensitive tilt-meter (≈ 10 - 8 rad/ Hz 1/2 at ≈ 30 mHz) would be important  As demonstrated during VRS1 payload swing is ok during normal conditions but..

8 AdV Review - November 3rd, 2008 8 Present Marionette and Ref. Mass DAC Noise  Reference mass actuator noise is compliant with AdV AdV VIRGO  Marionette actuator noise has to be reduced for AdV by about a factor 10 in the 10-30 Hz region (SAT R&D)

9 AdV Review - November 3rd, 2008 9 Marionette Actuation Range Optimization Calm Any  Marionette actuation range (and thus noise) can be already reduced by a factor 5, loosing only 1% of duty cycle  If tilt-meters will be put in action a calm condition on top-stage can be recovered, allowing at least a factor 8 reduction (by less 1% duty cycle) Volt

10 AdV Review - November 3rd, 2008 10 Marionette DAC Noise Reduction AdV starting point with a factor 5 DAC noise reduction AdV VIRGO

11 AdV Review - November 3rd, 2008 11 Present Performances vs AdV Specifications  Passive attenuation is OK  a new confirming test will be made in the next months  Payload swing is OK during normal environmental conditions  ID performance need to be enhanced during windy periods:  Tilt control as direct solution to reduce mirror swing below 200 mHz by a factor 10:  Operate high sensitive tilt-meters (difficult task) and piezo actuators  Investigate the possibility to extract the tilt signal combining the error signals of more SAs  Reduce actuation noise:  Selecting new low noise DAC (R&D: preliminary factor 1.5 obtained)  Splitting the action from only one to both cavity mirrors (factor 2)  Advanced filtering (enphaisis-de emphasis already tested on RM-Mirror)  Actuation optimization (factor 5 now)  Adaptive control strategy (new coil drivers with switch HN/LN config)

12 AdV Review - November 3rd, 2008 12 SAT Activities  SAT is called to make plans for the following activities:  Upgrade of the SA system (R&D activities):  Tilt Control:  Tilt-meters, piezoelectric actuators  Actuation noise:  ADC-DSP-DAC, Coil drivers  Upgrades:  Inverted Pendulum (IP)  Filter Zero (F0)  ACC, LVDT boards  Deliver plans for:  SR SA construction, assembly and integration  MC-DB-IB SAs upgrade

13 AdV Review - November 3rd, 2008 13 Tilt-Meter Status  Two Prototypes have been already assembled.  No problem in the electronics chain  Serious problems in the yielding of the flex joints (robustness).  New flex joint system mounted  Tests are being performed and will continue in the next months.

14 AdV Review - November 3rd, 2008 14 Piezoelectric Actuators Room for PZT accommodation Bottom ring Tilt meter  Tilt compensation was already addressed before VIRGO construction  Space for Piezos operation is already available on the bottom of IP platform

15 AdV Review - November 3rd, 2008 15 Piezoelectric Actuators Status  The three piezos P-239.30 have been purchased.  The driving board is being prepared.  The installation in SA Facility at EGO (SAFE) is progressing

16 AdV Review - November 3rd, 2008 16 Inverted Pendulum  A new IP has been conceived.  Monolithic Al legs:  higher structural modes, more robust and safe for piezos operation  First IP prototype built and on site, ready to be assembled in SAFE

17 AdV Review - November 3rd, 2008 17 Filter Zero and Accelerometers  The F0 design is being investigated to displace to higher frequency the crossbar resonances (benefit to vertical ID)  Analysis of the F0 crossbar resonance effects is in progress to understand the impact on the interferometer  The ACC sensitivity ( a few 10 -9 m/s 2 / (Hz )1/2 above 1 Hz) is adequate for AdV VIRGO but a few actions are required  Obsolete electronics upgrades  Spares preparation  New digital control boards  New monolithic ACC is being investigated by the Napoli-Salerno Group

18 AdV Review - November 3rd, 2008 18 SAT R&D Activities Implementation Plan

19 AdV Review - November 3rd, 2008 19 SAT R&D Manpower

20 AdV Review - November 3rd, 2008 20 SR Construction, Assembly and Integration  The SR SA chain will be a complete long Superattenuator.  preliminary specs: (G. Vajente, “Requirements for the Advanced Virgo Length Sensing and Control System”, VIR-083-A, 2008)  VIRGO design + R&D upgrades  PBS, WBS, cost estimates and manpower plan has been conceived: SAT MANAGEMENT PLAN (Issue 1 ready): (“SAT AdV Plan for R&D, SR Construction and Short SA Upgrade” VIR-091A-,2008)

21 AdV Review - November 3rd, 2008 21 SR Construction, Assembly and Integration SR SA ITEM 1 St. Filt. ITEM 2 F0 ITEM 3 F7 ITEM 4 IP ITEM 5 Safety Frame ITEM 6 Susp. Wires ITEM 7 Cabling ITEM 8 Acceler ITEM 9 Tools

22 AdV Review - November 3rd, 2008 22 SR Production and Manpower Plan

23 AdV Review - November 3rd, 2008 23 SR Installation Plan

24 AdV Review - November 3rd, 2008 24 SR Costs Evaluation

25 AdV Review - November 3rd, 2008 25 MC-IB-DB Systems Upgrade  OPTION 1: One extra filter stage  1 FS, F0 blades, IP Flex joint, Cabling Reshuf.  OPTION 2: More than one extra filter stage (up to 4)  Opt.1 +n. FS, IP Legs, Safety Struct., Full Cabling.

26 AdV Review - November 3rd, 2008 26 MC-IB-DB Systems Upgrade Plans

27 AdV Review - November 3rd, 2008 27 MC-IB-DB System Costs

28 AdV Review - November 3rd, 2008 28 Summary of Management Plan SIGNAL RECYCLING SUSPENSION  Time: 9 Months for item preparation + 13 weeks for assembly  Persons: minimum of 7 physicists/engineers + 5 technicians  Costs: 327 k€ + electronics (130 k€ - detailed plan in progress) SHORT TOWER UPGRADES  Time: 7-11 months for items preparation + 13 – 17 weeks  Persons: minimum of 7 physicists/engineers + 5 technicians  Costs: 216 k€ (option1), 359 k€ (MC:1FS, IB 2FS, DB 2FS) 398 k€ (MC:1FS, IB 3FS, DB 3FS), 437 k€ (MC:1FS, IB 2FS, DB 2FS) + electronics (300 k€ TBD)