COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM (CDBG) FISCAL YEAR 2016 2016 LMA Street Resurfacing Program Presented by: The City of Lakewood Department of Public Works Division of Engineering & Construction Mark Papke, PE, CPESC – City Engineer
2
What are the roadway conditions of the City? PCR = Pavement Condition Rating 2014 Overall Pavement Condition Ratings
8
Before Resurfacing After Resurfacing
9
PROPOSED 2016 LMA Street Resurfacing Street 2015 PCR LengthLast Year Paved - Type Chase441,340’2007 –Asphalt Surface Recycling Elbur 451,202’1992 – Mill-Fill Merl 54761’2007 –Asphalt Surface Recycling Newman421,017’1994 – Mill-Fill Project Service Area StreetLimitsCensus Tract Block Group ChaseClifton to Merl1605003 Elbur Clifton to Merl1605002 Merl Manor Park to Bunts1605003 NewmanFranklin to Madison1617002 CDBG - Data
10
Neighborhood Composition Housing 115 Single Family 17 Two-Family 1 Three Family 9 Apartments Other 1 Commercial 2 Vacant 1 Power substation
11
Budget PS&E $ 5,000 Construction $ 485,000 Inspection$ 2,500 Bid$ 250 Estimate$ 492,750 CDBG Request Amount $485,000
12
2016 Project Work Schedule Design Kickoff MeetingJan 50% Plan ReviewApr PS&EMay BiddingMay AwardJun ConstructionJul Project CompletionNov