1 Info on preliminary cabling request for LIU-PS S. Gilardoni PS-LIU 24 Feb. 2015

2 Introduction Goal: -Kick off the discussion on the preparation the cable requests -Start to explore with EN/EL the possibility to advance the installations during the next YETS and EYETS -Try to advance, at list partially, whenever possible, the interventions before LS2 -We will have soon a official EN/EL contact for cable matters This list reflect the current information I have but should be updated DICs should be issued as soon as possible if the information is available. Already, minimum information like the position in the tunnel of the equipments and the location of the power converters/electronics should be made available asap. If possible also the cable types. Remember also to ask for the removal of the unused or old cables.

3 Info available and/or that should be updated ElementSS/MUExisting install. Future installation Proposal resp. (TBC) Comment Injection bumpers 40 43 44365 J. M. CraveroRe-use existing cables New Septum 4242361 J. Borburgh J. M. Cravero New bumper 4141365J. M. CraveroNew bumper New kfa45 /5345/53362362 – tbcT. Kramer + J. Borburgh Will depend if KFA53 needed New SEM - injection MU42Not avail.BI - tbdPossible to re-use existing cables? Ionization profile monitor 82tbdM. Sapinski D. Bodart All new cables, power and aqn. Fast BLMssee EDMS 1157751 368368 - tbcBI - tbdOASIS crate already there Slow BLMssee EDMS 1157751 368368 – tbcBI - tbdKeep same position as today?

4 Info available and/or that should be updated ElementSS/MUExisting install. Future install. Proposal resp. (TBC) Comment Skew quadrupoles - QSKtbd152 S. PittetRe-use existing cables if possible Vertical correctors - DVTtdb152 S. PittetRe-use existing cables if possible Backleg windings - DHZEvery MU152 S. PittetRe-use existing cables Low energy quads – QDF-QDE Various MU 152 S. PittetRe-use existing cables Second Ionization profile monitor tbdM. Sapinski D. Bodart All new cables, power and aqn. Insertion magnetstbd J. M. CraveroNew installation New dumps47/48 plus second location 354 – tbc354 - tbcF.X. Nuiry New wire scanners54 64 65 68 85 To be found Probably as today BI - tbdReplacing existing install. Need cables for bunch-by-bunch

5 Info available and/or that should be updated ElementSS/MUExisting install. Future install. Proposal resp. (TBC) Comment New digital LLRFna353H. DamerauAll outside tunnel e-cloud monitor98355 M. TaborelliDone during YETS